16747 W RINALDI ST 91344

Certificate Information: 16747 W RINALDI ST 91344

Application / Permit
20014-10000-01183
Plan Check / Job No.
B20LA05138
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO NEW ADU. NEW 1 STORY ADDITION TO ADD BEDROOMS AND BATHROOMS. WORK PER WFPP
Permit Issued
Issued on 3/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ADAM HEGAZI
Corrections Issued 3/13/2020 ADAM HEGAZI
Plan Check Approved 3/16/2020 KEVIN MORALES
Issued 3/19/2020 LADBS
CofO in Progress 7/17/2020 MARK JOHNSON
Permit Finaled 12/18/2021 MICHAEL SMITH
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/13/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/13/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 3/13/2020 JEANIE LAM
Sewer availability Cleared 3/13/2020 JEANIE LAM
Grading Pre-Inspection Cleared 3/16/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2020 Not Ready for Inspection DANIEL ORRANTE
Underground Mechanical 4/28/2020 Approved DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 4/30/2020 Not Ready for Inspection MARK JOHNSON
Underground Mechanical 4/30/2020 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 5/4/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 5/28/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 5/28/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Approved MARK JOHNSON
Green Building Rough 5/28/2020 Approved MARK JOHNSON
HVAC-Rough 5/28/2020 Approved MARK JOHNSON
MERV13>=Rough 5/28/2020 Approved MARK JOHNSON
PLUMBING-Rough 5/28/2020 Approved MARK JOHNSON
Underground Mechanical 5/28/2020 Approved MARK JOHNSON
Insulation 6/2/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 6/2/2020 Approved GREGG CUMMINGS
Drywall Nailing 6/5/2020 Approved MARK JOHNSON
Final 6/30/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 6/30/2020 Approved MARK JOHNSON
Green Building Final 6/30/2020 Approved MARK JOHNSON
MERV13>=Final 6/30/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 6/30/2020 Approved MARK JOHNSON
Final 7/9/2020 Corrections Issued MARK JOHNSON
ELECTRICAL-Final 7/16/2020 Approved MARK JOHNSON
Final 7/16/2020 OK to Issue CofO MARK JOHNSON
HVAC-Final 7/16/2020 Approved MARK JOHNSON
PLUMBING-Final 7/16/2020 Approved MARK JOHNSON