1050 S QUEEN ANNE PL 90019
Certificate Information: 1050 S QUEEN ANNE PL 90019
- Application / Permit
- 20014-10000-01168
- Plan Check / Job No.
- B20LA05074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to rear of (E) SFD and enclosure the (E) front porch. Remodel entire house.
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RACHEL BEYENE |
| Corrections Issued | 3/12/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 3/13/2020 | MINA HABIB |
| Applicant returned to address corrections | 3/17/2020 | HELEN NGUYEN |
| Plan Check Approved | 3/17/2020 | HELEN NGUYEN |
| Issued | 3/18/2020 | LADBS |
| CofO in Progress | 12/29/2020 | STUART CHAPMAN |
| No Progress | 2/17/2022 | STUART CHAPMAN |
| CofO in Progress | 2/22/2022 | SCOTT FINNILA |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
| CofO Issued | 2/26/2022 | DEROLD HAUFF |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | ELAINE LEI |
| Sewer availability | Cleared | 3/12/2020 | ELAINE LEI |
Contact Information
| Engineer | Chi,, Joseph Chiwol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/1/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/8/2020 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 4/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 4/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 4/15/2020 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 4/24/2020 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 5/12/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/14/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/14/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 5/14/2020 | Approved | STUART CHAPMAN |
| METHANE-Rough | 5/14/2020 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 5/14/2020 | Approved | STUART CHAPMAN |
| Wood Frame | 5/14/2020 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/19/2020 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/19/2020 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/19/2020 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 6/19/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 6/19/2020 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/13/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/13/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/13/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/13/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/27/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 8/4/2020 | Approved | STUART CHAPMAN |
| Insulation | 8/5/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 9/8/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/8/2020 | Corrections Issued | STUART CHAPMAN |
| Shower Pan | 9/8/2020 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/1/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/2/2020 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 10/2/2020 | Approved | STUART CHAPMAN |
| Final | 12/21/2020 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/21/2020 | Approved | STUART CHAPMAN |
| Green Building Final | 12/21/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 12/21/2020 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 12/28/2020 | Approved | STUART CHAPMAN |
| Final | 12/28/2020 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 12/28/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/28/2020 | Approved | STUART CHAPMAN |
| Smoke Detectors | 12/28/2020 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 2/17/2022 | Approved | STUART CHAPMAN |