1346 E 57TH ST 90011

Certificate Information: 1346 E 57TH ST 90011

Application / Permit
20014-10000-01165
Plan Check / Job No.
B20LA05058
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) detached garage and "convert existing accessory building to detached ADU per state law GCS 65852.2(e)(1)(A)".
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 HELEN NGUYEN
Corrections Issued 3/20/2020 HELEN NGUYEN
Applicant returned to address corrections 6/24/2020 HELEN NGUYEN
Plan Check Approved 7/22/2020 HELEN NGUYEN
Issued 7/28/2020 APPLICANT
Building Plans Picked Up 7/28/2020 APPLICANT
CofO in Progress 12/7/2022 ALEJANDRO DE ARTOLA
Permit Finaled 12/10/2022 DEROLD HAUFF
CofO Issued 12/10/2022 DEROLD HAUFF
Permit Finaled 12/10/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/23/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/24/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 4/24/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 4/24/2020 CECILIO NAVARRO
Sewer availability Cleared 5/7/2020 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 5/29/2020 HELEN JADALI

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor C G S Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2020 Corrections Issued ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 9/25/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 10/20/2020 Corrections Issued DONALD CRICHLOW
PLUMBING-Rough 10/20/2020 Corrections Issued DONALD CRICHLOW
Wood Frame 10/20/2020 Corrections Issued DONALD CRICHLOW
BUILDING-Rough-Frame 10/28/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 10/28/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 10/28/2020 Approved ROBERT MCDOWELL
Sewer 10/28/2020 Not Ready for Inspection ROBERT MCDOWELL
Insulation 11/9/2020 Not Ready for Inspection JOSEPH MCGARRY
Sewer 11/9/2020 Approved JOSEPH MCGARRY
Gas Test 11/19/2020 Approved ROBERT MCDOWELL
Insulation 11/19/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 11/19/2020 Approved ROBERT MCDOWELL
Drywall Nailing 12/1/2020 Approved DAVID FEILER
Green Building Rough 12/1/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 3/30/2021 Approved DAVID FEILER
Final 3/30/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 3/30/2021 Approved DAVID FEILER
Green Building Final 3/30/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 3/30/2021 Approved DAVID FEILER
ELECTRICAL-Final 4/19/2021 Approved ROBERT MCDOWELL
Final 4/19/2021 Corrections Issued ROBERT MCDOWELL
HVAC-Final 4/19/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/19/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 4/19/2021 Approved ROBERT MCDOWELL
Final 5/19/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 9/23/2022 No Access for Inspection SHAVONNE ESPINOZA
Final 9/23/2022 No Access for Inspection SHAVONNE ESPINOZA
PLUMBING-Final 9/23/2022 No Access for Inspection SHAVONNE ESPINOZA
Final 10/6/2022 Corrections Issued SHAVONNE ESPINOZA
Final 10/25/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/23/2022 Corrections Issued JULIAN AMAYA
Final 12/6/2022 OK to Issue CofO ALEJANDRO DE ARTOLA