3527 N LIFUR AVE 90032
Certificate Information: 3527 N LIFUR AVE 90032
- Application / Permit
- 20014-10000-01164
- Plan Check / Job No.
- B20LA05052
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 35'4"X30' ATTACHED ADU PER ORDINANCE, ATTACHED TO (E) GARAGE
- Permit Issued
- Issued on 12/13/2020
- Issuing Office
- Current Status
- CofO Issued on 5/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | AMIR DANAI |
| Corrections Issued | 4/7/2020 | AMIR DANAI |
| Quality Review Completed | 4/22/2020 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 5/15/2020 | APPLICANT |
| Applicant returned to address corrections | 7/22/2020 | AMIR DANAI |
| Plan Check Approved | 12/4/2020 | AMIR DANAI |
| Issued | 12/13/2020 | APPLICANT |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| CofO in Progress | 1/23/2024 | AMY COLIN |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
| Permit Finaled | 5/9/2024 | DEROLD HAUFF |
| CofO Issued | 5/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 5/14/2020 | DONALD CRICHLOW |
| Address approval | Cleared | 6/4/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/5/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 6/9/2020 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 6/10/2020 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 6/10/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 7/6/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 12/4/2020 | AMIR DANAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2021 | Not Ready for Inspection | COREY HUPP |
| Pre-Inspection | 2/4/2021 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 3/4/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 3/18/2021 | No Access for Inspection | COREY HUPP |
| Sewer | 3/24/2021 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 3/24/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2021 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/29/2021 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 5/20/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/14/2021 | Partial Inspection | COREY HUPP |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 6/14/2021 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Approval | COREY HUPP |
| HVAC-Rough | 9/22/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 3/31/2022 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 3/31/2022 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 3/31/2022 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 3/31/2022 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 4/15/2022 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 4/15/2022 | Approved | RUBEN SALAS |
| Insulation | 6/3/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 8/8/2022 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Approved | AMY COLIN |
| Drywall Nailing | 3/9/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/9/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 12/1/2023 | Approved | AMY COLIN |
| Final | 12/1/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/1/2023 | Approved | AMY COLIN |
| Green Building Final | 12/1/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 12/1/2023 | Approved | AMY COLIN |
| Smoke Detectors | 12/1/2023 | Approved | AMY COLIN |
| Final | 1/23/2024 | OK to Issue CofO | AMY COLIN |