3527 N LIFUR AVE 90032

Certificate Information: 3527 N LIFUR AVE 90032

Application / Permit
20014-10000-01164
Plan Check / Job No.
B20LA05052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 35'4"X30' ATTACHED ADU PER ORDINANCE, ATTACHED TO (E) GARAGE
Permit Issued
Issued on 12/13/2020
Issuing Office
Current Status
CofO Issued on 5/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 AMIR DANAI
Corrections Issued 4/7/2020 AMIR DANAI
Quality Review Completed 4/22/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 5/15/2020 APPLICANT
Applicant returned to address corrections 7/22/2020 AMIR DANAI
Plan Check Approved 12/4/2020 AMIR DANAI
Issued 12/13/2020 APPLICANT
Building Plans Picked Up 12/28/2020 APPLICANT
CofO in Progress 1/23/2024 AMY COLIN
Permit Finaled 5/9/2024 DEROLD HAUFF
Permit Finaled 5/9/2024 DEROLD HAUFF
CofO Issued 5/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 5/14/2020 DONALD CRICHLOW
Address approval Cleared 6/4/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/5/2020 CECILIO NAVARRO
Sewer availability Cleared 6/5/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 6/9/2020 PATRICK MISCHLICH
Low Impact Development Cleared 6/10/2020 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 6/10/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 7/6/2020 MATTHEW CRAIG
GPI Written Notices Cleared 12/4/2020 AMIR DANAI

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2021 Not Ready for Inspection COREY HUPP
Pre-Inspection 2/4/2021 Approved COREY HUPP
Excavation/Setback/Form/Re-Bar 2/9/2021 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 3/4/2021 Corrections Issued COREY HUPP
PLUMBING-Rough 3/4/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/18/2021 No Access for Inspection COREY HUPP
Sewer 3/24/2021 Approved CRAIG VAUGHAN
Underground Mechanical 3/24/2021 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/3/2021 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/13/2021 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/14/2021 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/29/2021 Partial Approval CRAIG VAUGHAN
Pre-Inspection 5/20/2021 Approved COREY HUPP
BUILDING-Rough-Frame 6/14/2021 Partial Inspection COREY HUPP
Green Building Rough 6/14/2021 Not Ready for Inspection COREY HUPP
Verify Sprinkler Sign Off 6/14/2021 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval COREY HUPP
HVAC-Rough 9/22/2021 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 3/31/2022 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 3/31/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 3/31/2022 Approved RUBEN SALAS
PLUMBING-Rough 3/31/2022 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 4/15/2022 Approved RUBEN SALAS
PLUMBING-Rough 4/15/2022 Approved RUBEN SALAS
Insulation 6/3/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Corrections Issued AMY COLIN
Interior/Exterior Lathing 8/8/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Approved AMY COLIN
Drywall Nailing 3/9/2023 Approved AMY COLIN
Interior/Exterior Lathing 3/9/2023 Approved AMY COLIN
BUILDING-Rough-Frame 12/1/2023 Approved AMY COLIN
Final 12/1/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 12/1/2023 Approved AMY COLIN
Green Building Final 12/1/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved AMY COLIN
Service/Power Release 12/1/2023 Approved AMY COLIN
Smoke Detectors 12/1/2023 Approved AMY COLIN
Final 1/23/2024 OK to Issue CofO AMY COLIN