1315 N GENESEE AVE 90046
Certificate Information: 1315 N GENESEE AVE 90046
- Application / Permit
- 20014-10000-01155
- Plan Check / Job No.
- B20LA05019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BATHROOM ADDITION (16'-9" X 9'-4") AT REAR OF (E) S.F.D.-ONESTORY & KITCHEN CABINETS. ADD SKYLIGHT & EXISTING BATHROOM
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/12/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 3/19/2020 | SINA KHOSRAVI |
| Plan Check Approved | 3/27/2020 | MONICA RAMIREZ |
| Issued | 4/27/2021 | APPLICANT |
| Building Plans Picked Up | 5/12/2021 | APPLICANT |
| CofO in Progress | 1/24/2023 | STUART CHAPMAN |
| Permit Finaled | 2/15/2023 | DEROLD HAUFF |
| CofO Issued | 2/15/2023 | DEROLD HAUFF |
| Permit Finaled | 2/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/12/2020 | THOMAS LANG |
| HPOZ | Cleared | 3/16/2020 | AMANDA KAINER |
Contact Information
| Contractor | Home Remodeling And Design; Lic. No.: 610121-B | 1107 FAIR OAKS AVENUE 424 SOUTH PASADENA, CA 91030 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 8/12/2021 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/26/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/26/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 8/26/2021 | Approved | RAUL BARAJAS |
| HVAC-Rough | 8/26/2021 | Partial Inspection | RAUL BARAJAS |
| Insulation | 9/3/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/14/2021 | Approved | JESUS PINEDA |
| Shower Pan | 9/14/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/17/2021 | Approved | RAUL BARAJAS |
| Final | 12/20/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/20/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 12/20/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/20/2021 | Approved | RAUL BARAJAS |
| Final | 6/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 6/14/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 12/15/2022 | OK for TCO | STUART CHAPMAN |
| Final | 12/30/2022 | OK for TCO | STUART CHAPMAN |
| Service/Power Release | 12/30/2022 | Approved | STUART CHAPMAN |
| Final | 1/24/2023 | OK to Issue CofO | STUART CHAPMAN |