3139 N DORCHESTER AVE 90032
Certificate Information: 3139 N DORCHESTER AVE 90032
- Application / Permit
- 20014-10000-01149
- Plan Check / Job No.
- B20LA04985
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT REAR OF (E) SFD (1 OF 2)
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 9/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2020 | KEVIN MORALES |
| Corrections Issued | 3/11/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 7/29/2020 | AMIR DANAI |
| Plan Check Approved | 8/17/2020 | CARLOS MONTES |
| Issued | 8/17/2020 | APPLICANT |
| Building Plans Picked Up | 8/19/2020 | APPLICANT |
| CofO in Progress | 8/31/2021 | SCOTT FINNILA |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
| CofO Issued | 9/22/2021 | DEROLD HAUFF |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/12/2020 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 8/10/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Sanz Construction Inc; Lic. No.: 896113-B | 2724 WEST MAIN STREET ALHAMBRA, CA 91801 |
| Engineer | Chan,, Terence Ka-Hing; Lic. No.: C48893 | 3579 E FOOTHILL BLVD 206 PASADENA, CA 91107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2020 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 10/13/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 11/19/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 11/19/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 11/19/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 11/30/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 11/30/2020 | Approved | COREY HUPP |
| Green Building Rough | 11/30/2020 | Not Ready for Inspection | COREY HUPP |
| Insulation | 12/7/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 12/7/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | COREY HUPP |
| Green Building Rough | 12/9/2020 | Approved | COREY HUPP |
| Drywall Nailing | 12/16/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 12/16/2020 | Approved | COREY HUPP |
| Final | 6/1/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 6/1/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 6/1/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 7/27/2021 | Partial Inspection | COREY HUPP |
| Green Building Final | 7/27/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 7/27/2021 | Approved | COREY HUPP |
| ELECTRICAL-Final | 8/30/2021 | Approved | SCOTT FINNILA |
| Final | 8/30/2021 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 8/30/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 8/30/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 8/30/2021 | Approved | SCOTT FINNILA |