620 E VERNON AVE 90291

Certificate Information: 620 E VERNON AVE 90291

Application / Permit
20014-10000-01141
Plan Check / Job No.
B20LA04908
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR 1-STORY SFD OF 286 SQFT ADDITION. NEW 3RD PARKING / RESTRIPING OVER CONCRETE PAD PLUS INTERIOR REMODELING. ALL NEW ROOF AND ROOF FRAMING.
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 RAHEL BEYENE
Corrections Issued 3/20/2020 RAHEL BEYENE
Applicant returned to address corrections 4/24/2020 RAHEL BEYENE
Applicant returned to address corrections 6/12/2020 RAHEL BEYENE
Applicant returned to address corrections 6/26/2020 RAHEL BEYENE
Applicant returned to address corrections 8/25/2020 RAHEL BEYENE
Plan Check Approved 9/9/2020 RAHEL BEYENE
Issued 9/29/2020 APPLICANT
Building Plans Picked Up 10/2/2020 APPLICANT
CofO in Progress 12/23/2021 ENRIQUE MIRELES
CofO in Progress 12/23/2021 ENRIQUE MIRELES
Permit Finaled 12/30/2021 DANIEL ORRANTE
CofO Issued 12/30/2021 DANIEL ORRANTE
Permit Finaled 12/30/2021 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 3/31/2020 TERRI OSBORNE
Miscellaneous Cleared 3/31/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 5/28/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 5/28/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/28/2020 HISASHI KOBAYAKAWA
Coastal Zone Cleared 6/22/2020 TERRI OSBORNE
Specific Plan Cleared 7/2/2020 KEVIN FULTON
Coastal Zone Cleared 7/21/2020 TERRI OSBORNE
Low Impact Development Cleared 8/13/2020 MITESH PATEL

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/10/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 11/16/2020 Corrections Issued DAVID HEINE
METHANE-Barrier 11/16/2020 Corrections Issued DAVID HEINE
METHANE-Subgrade 11/16/2020 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 11/19/2020 Corrections Issued JUAN VALENZUELA
METHANE-Barrier 11/19/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 11/19/2020 Not Ready for Inspection JUAN VALENZUELA
Underground Mechanical 11/19/2020 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/23/2020 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/24/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 12/23/2020 Partial Approval DAVID HEINE
METHANE-Rough 12/23/2020 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Corrections Issued JOHNNY MIRANDA
Shower Pan 2/10/2021 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 2/11/2021 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 2/11/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval JOHNNY MIRANDA
METHANE-Rough 2/11/2021 Approved JOHNNY MIRANDA
Shower Pan 2/11/2021 Approved JOHNNY MIRANDA
Special/Order Compliance 2/11/2021 Partial Inspection PIERRE VEGA
Wood Frame 2/11/2021 Partial Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 2/18/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 2/18/2021 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 2/18/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 2/22/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 2/22/2021 Approved JOHNNY MIRANDA
Green Building Rough 2/22/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/22/2021 Approved JOHNNY MIRANDA
Insulation 2/24/2021 Approved JOHNNY MIRANDA
Drywall Nailing 3/22/2021 Approved RICHARD STEINBACH
ELECTRICAL-Final 9/30/2021 Approved JOHNNY MIRANDA
Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 9/30/2021 Approved JOHNNY MIRANDA
HVAC-Final 9/30/2021 Corrections Issued JOHNNY MIRANDA
METHANE-Barrier 9/30/2021 Approved JOHNNY MIRANDA
METHANE-Subgrade 9/30/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 9/30/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 9/30/2021 Approved JOHNNY MIRANDA
HVAC-Final 12/22/2021 Corrections Issued ENRIQUE MIRELES
Final 12/23/2021 OK to Issue CofO ENRIQUE MIRELES