13070 W VENTURA BLVD 91604

Certificate Information: 13070 W VENTURA BLVD 91604

Application / Permit
20014-10000-01136
Plan Check / Job No.
B20LA04867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION AT REAR OF EXISTING SFD. INSTALL FIRE SPRINKLERS THROUGHOUT (SEPARATE PERMIT REQUIRED).
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
Issued on 4/21/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ALBERT SERVIN
Corrections Issued 3/24/2020 ALBERT SERVIN
Quality Review Completed 3/25/2020 KEN GILL
Applicant returned to address corrections 4/29/2020 ALBERT SERVIN
Applicant returned to address corrections 9/10/2020 ALBERT SERVIN
Applicant returned to address corrections 2/16/2021 ALBERT SERVIN
Applicant returned to address corrections 2/23/2021 ALBERT SERVIN
Plan Check Approved 3/5/2021 ALBERT SERVIN
Issued 4/21/2021 APPLICANT
Building Plans Picked Up 4/26/2021 APPLICANT
Green Plans Picked Up 12/29/2021 APPLICANT

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 4/3/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 7/21/2020 GABRIEL ROBLES
Sewer availability Cleared 7/22/2020 GABRIEL ROBLES
Green Code Cleared 12/24/2020 AARON COSTA
Low Impact Development Cleared 1/21/2021 SARAH YOUSSEF
Grading Pre-Inspection Cleared 1/22/2021 ALBERT SERVIN
GPI Written Notices Cleared 2/1/2021 ALBERT SERVIN
Roof/Waste drainage to street Cleared 2/26/2021 ADRIAN CASTRO

Contact Information

Contractor Landmark Building & Design Inc; Lic. No.: 982610-B 4717 VAN NUYS BLVD STE 104      SHERMAN OAKS, CA 91403
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 11/12/2021 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/15/2021 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/22/2021 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 2/14/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 2/17/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 2/17/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 2/23/2022 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 3/29/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 5/10/2022 Conditional Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/20/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 5/20/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/20/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 5/24/2022 Approved ARAM AVEDISIAN
HVAC-Rough 5/24/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 5/24/2022 Approved ARAM AVEDISIAN
Insulation 6/1/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 6/7/2022 Conditional Approval CALEB MEISTER
Final 6/7/2022 Corrections Issued CALEB MEISTER
Insulation 6/7/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 6/14/2022 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 6/24/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 6/24/2022 Approved CALEB MEISTER
Shower Pan 6/24/2022 Approved CALEB MEISTER