9347 N WOODLEY AVE 91343

Certificate Information: 9347 N WOODLEY AVE 91343

Application / Permit
20014-10000-01135
Plan Check / Job No.
B20LA04862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION ( 10ft x 20ft) AND CONVERT EXISTING DETACHED TWO CAR GARAGE TO ADU
Permit Issued
Issued on 7/2/2020
Issuing Office
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 TSE MING HUANG
Corrections Issued 3/17/2020 TSE MING HUANG
Plan Check Approved 6/24/2020 TSE MING HUANG
Issued 7/2/2020 APPLICANT
Building Plans Picked Up 7/2/2020 APPLICANT
CofO in Progress 2/9/2021 ARTHUR SARGSYAN
CofO in Progress 2/9/2021 ARTHUR SARGSYAN
No Progress 2/22/2021 JACK KARGODORIAN
CofO in Progress 2/24/2021 JACK KARGODORIAN
CofO Issued 4/24/2021 MICHAEL SMITH
Permit Finaled 4/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 4/20/2020 GABRIEL ROBLES
Low Impact Development Cleared 5/26/2020 ORVAL HERNANDEZ-MARCIAL
Grading Pre-Inspection Cleared 5/27/2020 PATRICK MISCHLICH
Address approval Cleared 6/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/2/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/5/2020 ADRIAN CASTRO

Contact Information

Contractor Logical & Innovative Construction Group; Lic. No.: 1042051-B 756 S BROADWAY STE 409      LOS ANGELES, CA 90014

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2020 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 7/13/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 7/13/2020 Not Ready for Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 7/14/2020 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/16/2020 Corrections Issued DANIEL DREW
Footing/Foundation/Slab 7/16/2020 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 7/20/2020 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 7/22/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 7/23/2020 Approved MICHAEL TEMPLE
Gas Test 7/30/2020 Corrections Issued DANIEL DREW
PLUMBING-Rough 8/4/2020 Partial Approval DONALD SUNSERI
Underground Mechanical 8/4/2020 Approved DONALD SUNSERI
Wood Frame 8/7/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 9/22/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/22/2020 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval JOSEPH SAGEN
Special/Order Compliance 10/1/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Partial Inspection WILLIAM KUEHN
HVAC-Rough 10/9/2020 Approved WILLIAM KUEHN
Insulation 11/9/2020 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/11/2020 Approved ARTHUR SARGSYAN
Final 12/11/2020 Corrections Issued ARTHUR SARGSYAN
Green Building Final 12/11/2020 Approved ARTHUR SARGSYAN
Green Building Rough 12/11/2020 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/11/2020 Approved ARTHUR SARGSYAN
Final 2/1/2021 Corrections Issued ARTHUR SARGSYAN
Pre-Inspection 2/1/2021 Partial Inspection MICHAEL TEMPLE
Final 2/8/2021 OK to Issue CofO ARTHUR SARGSYAN