609 1/2 E VICTORIA AVE 90291
Certificate Information: 609 1/2 E VICTORIA AVE 90291
- Application / Permit
- 20014-10000-01114
- Plan Check / Job No.
- B20LA04820
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING [REAR].
- Permit Issued
- Issued on 5/29/2020
- Issuing Office
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2020 | KEVIN MORALES |
| Corrections Issued | 3/10/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 5/12/2020 | JESSE JIMENEZ |
| Plan Check Approved | 5/29/2020 | KEVIN MORALES |
| Issued | 5/29/2020 | APPLICANT |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| CofO in Progress | 3/18/2021 | ENRIQUE MIRELES |
| Permit Finaled | 4/9/2021 | VINCENT COTTON |
| CofO Issued | 4/9/2021 | VINCENT COTTON |
| Permit Finaled | 4/9/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | PAMELA TENEZA |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | EMIL KYUPELYAN |
| ZA Case | Cleared | 3/10/2020 | KENTON TRINH |
| Coastal Zone | Cleared | 5/7/2020 | ANNA VIDAL |
| ZA Case | Cleared | 5/7/2020 | ANNA VIDAL |
| Specific Plan | Cleared | 5/19/2020 | SIENNA KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2020 | Partial Approval | DAVID HEINE |
| Deputy Drilled-In Anchors | 7/29/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 7/30/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 8/11/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 8/20/2020 | Not Ready for Inspection | DAVID HEINE |
| Footing/Foundation/Slab | 8/20/2020 | Approved | DAVID HEINE |
| Green Building Rough | 8/20/2020 | Not Ready for Inspection | DAVID HEINE |
| Pre-Inspection | 8/20/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Partial Approval | ENRIQUE MIRELES |
| HVAC-Rough | 10/21/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/21/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/30/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/30/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/30/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/5/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 11/5/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 11/18/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/20/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/24/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/9/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/18/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Green Building Final | 3/18/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/18/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/18/2021 | Approved | ENRIQUE MIRELES |