609 1/2 E VICTORIA AVE 90291

Certificate Information: 609 1/2 E VICTORIA AVE 90291

Application / Permit
20014-10000-01114
Plan Check / Job No.
B20LA04820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING [REAR].
Permit Issued
Issued on 5/29/2020
Issuing Office
Current Status
CofO Issued on 4/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/10/2020 KEVIN MORALES
Corrections Issued 3/10/2020 KEVIN MORALES
Applicant returned to address corrections 5/12/2020 JESSE JIMENEZ
Plan Check Approved 5/29/2020 KEVIN MORALES
Issued 5/29/2020 APPLICANT
Building Plans Picked Up 5/29/2020 APPLICANT
CofO in Progress 3/18/2021 ENRIQUE MIRELES
Permit Finaled 4/9/2021 VINCENT COTTON
CofO Issued 4/9/2021 VINCENT COTTON
Permit Finaled 4/9/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/10/2020 PAMELA TENEZA
Roof/Waste drainage to street Cleared 3/10/2020 EMIL KYUPELYAN
ZA Case Cleared 3/10/2020 KENTON TRINH
Coastal Zone Cleared 5/7/2020 ANNA VIDAL
ZA Case Cleared 5/7/2020 ANNA VIDAL
Specific Plan Cleared 5/19/2020 SIENNA KUO

Contact Information

Contractor Owner-Builder       ,
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2020 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 7/29/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 7/30/2020 Approved DAVID HEINE
PLUMBING-Rough 8/11/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 8/20/2020 Not Ready for Inspection DAVID HEINE
Footing/Foundation/Slab 8/20/2020 Approved DAVID HEINE
Green Building Rough 8/20/2020 Not Ready for Inspection DAVID HEINE
Pre-Inspection 8/20/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Partial Approval ENRIQUE MIRELES
HVAC-Rough 10/21/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 10/21/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 10/30/2020 Approved ENRIQUE MIRELES
HVAC-Rough 10/30/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/30/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/5/2020 Corrections Issued ENRIQUE MIRELES
Green Building Rough 11/5/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/12/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/12/2020 Approved ENRIQUE MIRELES
Insulation 11/18/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/20/2020 Approved ENRIQUE MIRELES
Drywall Nailing 11/24/2020 Approved ENRIQUE MIRELES
Service/Power Release 2/9/2021 Corrections Issued ENRIQUE MIRELES
Final 3/18/2021 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 3/18/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/18/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/18/2021 Approved ENRIQUE MIRELES
Smoke Detectors 3/18/2021 Approved ENRIQUE MIRELES