3232 W MADERA AVE 90039

Certificate Information: 3232 W MADERA AVE 90039

Application / Permit
20014-10000-01096
Plan Check / Job No.
B20LA04732
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD
Permit Issued
Issued on 7/23/2020
Issuing Office
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Assigned to Plan Check Engineer 3/9/2020 MONICA RAMIREZ
Corrections Issued 3/9/2020 MONICA RAMIREZ
Applicant returned to address corrections 5/19/2020 AUNG SOE
Plan Check Approved 7/13/2020 RICARDO RAMIREZ
Issued 7/23/2020 APPLICANT
Building Plans Picked Up 7/23/2020 APPLICANT
CofO in Progress 12/4/2020 OSVALDO PARAMO
CofO in Progress 12/4/2020 OSVALDO PARAMO
CofO in Progress 12/4/2020 OSVALDO PARAMO
Permit Finaled 12/10/2020 DEROLD HAUFF
CofO Issued 12/10/2020 DEROLD HAUFF
Permit Finaled 12/10/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/9/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 3/9/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Palaha,, Jiwanjit Singh; Lic. No.: C49533 20529 E RANCHO SAN JOSE DR      COVINA, CA 91724

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/30/2020 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 8/5/2020 Approved ELMER BLAND
Excavation/Setback/Form/Re-Bar 8/12/2020 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/12/2020 Approved OSVALDO PARAMO
Wood Frame 8/18/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Approved OSVALDO PARAMO
ELECTRICAL-Rough 9/1/2020 Corrections Issued OSVALDO PARAMO
HVAC-Rough 9/1/2020 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 9/1/2020 Corrections Issued OSVALDO PARAMO
Wood Frame 9/1/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 9/3/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 9/3/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/8/2020 Order to Comply Issued OSVALDO PARAMO
Green Building Rough 9/8/2020 Approved OSVALDO PARAMO
HVAC-Rough 9/8/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/10/2020 Approved OSVALDO PARAMO
Insulation 9/10/2020 Approved OSVALDO PARAMO
Special/Order Compliance 9/10/2020 Approved OSVALDO PARAMO
Wood Frame 9/10/2020 Approved OSVALDO PARAMO
Drywall Nailing 9/15/2020 Not Ready for Inspection OSVALDO PARAMO
Shower Pan 9/15/2020 Approved OSVALDO PARAMO
Drywall Nailing 9/17/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/17/2020 Approved OSVALDO PARAMO
Final 10/6/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 10/6/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/6/2020 Approved OSVALDO PARAMO
Final 10/14/2020 OK to Issue CofO OSVALDO PARAMO