340-342 E 79TH ST 90003

Certificate Information: 340-342 E 79TH ST 90003

Application / Permit
20014-10000-01092
Plan Check / Job No.
B20LA04726
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT A SFD TO DUPLEX BY ADDING PARTITION WALL PER WFPP. (N) CARPORT TO BE ATTACHED PER CITY STANDARD PLANS.
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Assigned to Plan Check Engineer 3/9/2020 FERNANDO FLORES
Corrections Issued 3/9/2020 FERNANDO FLORES
Plan Check Approved 3/16/2020 AUNG SOE
Issued 1/20/2022 APPLICANT
CofO in Progress 1/10/2023 LILIANA PORTILLO
No Progress 2/8/2023 SCOTT FINNILA
CofO in Progress 11/22/2023 SCOTT FINNILA
Permit Finaled 12/7/2023 DEROLD HAUFF
CofO Issued 12/7/2023 DEROLD HAUFF
Permit Finaled 12/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/16/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/16/2020 JEANIE LAM
Permit Cleared 3/16/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 3/16/2020 JEANIE LAM
Sewer availability Cleared 3/16/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/2/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 2/2/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Partial Approval ALIZAH MAYAGOITIA
Special/Order Compliance 2/8/2022 Partial Inspection AMY COLIN
Wood Frame 2/8/2022 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 2/22/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 2/22/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/13/2022 Not Ready for Inspection LILIANA PORTILLO
Final 5/13/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 5/13/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 5/13/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/13/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/15/2022 Approved LILIANA PORTILLO
Final 6/15/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 6/15/2022 Approved LILIANA PORTILLO
Smoke Detectors 6/15/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/29/2022 Approved LILIANA PORTILLO
Final 7/29/2022 Conditional Approval LILIANA PORTILLO
HVAC-Final 7/29/2022 Approved LILIANA PORTILLO
PLUMBING-Final 7/29/2022 Approved LILIANA PORTILLO
Final 1/9/2023 OK to Issue CofO LILIANA PORTILLO