5218 E BARKER DR 90042
Certificate Information: 5218 E BARKER DR 90042
- Application / Permit
- 20014-10000-01090
- Plan Check / Job No.
- B20LA04720
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) crawl space into a new recreation room.
- Permit Issued
- Issued on 6/9/2020
- Issuing Office
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | ALBERT SERVIN |
| Corrections Issued | 3/24/2020 | ALBERT SERVIN |
| Quality Review Completed | 3/25/2020 | KEN GILL |
| Building Plans Picked Up | 4/2/2020 | APPLICANT |
| Green Plans Picked Up | 5/19/2020 | APPLICANT |
| Plan Check Approved | 5/27/2020 | ALBERT SERVIN |
| Issued | 6/9/2020 | APPLICANT |
| CofO in Progress | 9/30/2025 | DAVID WILLIAMS |
| No Progress | 9/30/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 9/30/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 9/30/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 10/3/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/23/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 4/23/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 4/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/23/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 5/15/2020 | ALBERT SERVIN |
| Grading Pre-Inspection | Cleared | 5/22/2020 | ALBERT SERVIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Velasco,, Jose Luis; Lic. No.: C76091 | 8371 BENJAMIN DR HUNTINGTON BEACH, CA 92647 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/9/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/9/2021 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/4/2021 | No Access for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/8/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 10/8/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/12/2021 | Approved | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 8/30/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/6/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/6/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 9/6/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/6/2023 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 9/6/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/18/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/18/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/18/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/18/2023 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 10/18/2023 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 10/18/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 10/20/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 11/1/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 11/1/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/1/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 8/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 8/28/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/15/2025 | Corrections Issued | DAVID WILLIAMS |
| Final | 9/29/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 9/30/2025 | OK to Issue CofO | DAVID WILLIAMS |