11041 S BARING CROSS ST 90044
Certificate Information: 11041 S BARING CROSS ST 90044
- Application / Permit
- 20014-10000-01072
- Plan Check / Job No.
- B20LA04663
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 375 SQ FT TO EXISTING 2 CAR GARAGE TO CONVERT THE GARAGE INTO A 1 STORY ADU. PER WFPP. ADD 1 BATHROOM, A SMALL KITCHEN AND 1 BEDROOM.
- Permit Issued
- Issued on 9/9/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 4/27/2020 | SALVADOR QUINTANILLA |
| Quality Review Completed | 4/29/2020 | KEN GILL |
| Green Plans Picked Up | 7/10/2020 | APPLICANT |
| Applicant returned to address corrections | 9/15/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 1/19/2021 | SALVADOR QUINTANILLA |
| Issued | 9/9/2021 | APPLICANT |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| CofO in Progress | 12/7/2022 | JOHN KLARIN |
| No Progress | 3/18/2023 | MICHAEL PELHAM |
| CofO in Progress | 4/20/2023 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
| CofO Issued | 4/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2020 | JEANIE LAM |
| Permit | Cleared | 6/2/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 6/4/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2020 | JEANIE LAM |
| ZA Case | Cleared | 6/17/2020 | TERRI OSBORNE |
| Green Code | Cleared | 7/9/2020 | KHEDER ALRAZAA |
| Construction near power lines | Cleared | 12/11/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | New,, Rod G; Lic. No.: S3419 | 2870 PINE SLOPE DR CUMMING, GA 30041 |
| Engineer | Pirathiviraj,, Sivasubramaniam; Lic. No.: C71662 | 3 ALBANY IRVINE, CA 92604 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/26/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 1/27/2022 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/3/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/24/2022 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 2/24/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 6/10/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 6/13/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 6/16/2022 | No Access for Inspection | JOHN KLARIN |
| HVAC-Rough | 6/21/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/29/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/7/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/22/2022 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 7/26/2022 | No Access for Inspection | ANSON MAGLASANG |
| Gas Test | 8/3/2022 | Approved | JOHN KLARIN |
| Green Building Final | 8/30/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 9/20/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 9/20/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/3/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 10/3/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 10/12/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/18/2022 | Corrections Issued | JOHN KLARIN |
| Pre-Inspection | 10/18/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 10/27/2022 | Approved | JOHN KLARIN |
| Final | 10/27/2022 | Conditional Approval | JOHN KLARIN |
| Green Building Final | 10/27/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 10/27/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/27/2022 | Approved | JOHN KLARIN |
| Final | 12/7/2022 | OK to Issue CofO | JOHN KLARIN |