801 E 118TH ST 90059
Certificate Information: 801 E 118TH ST 90059
- Application / Permit
- 20014-10000-01032
- Plan Check / Job No.
- B20LA04457
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION OF RECREATION ROOM WITH HALF BATH TO EXISTING GARAGE.
- Permit Issued
- Issued on 7/22/2020
- Issuing Office
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | MONICA RAMIREZ |
| Corrections Issued | 3/5/2020 | MONICA RAMIREZ |
| Plan Check Approved | 7/8/2020 | RICARDO RAMIREZ |
| Issued | 7/22/2020 | APPLICANT |
| Building Plans Picked Up | 7/23/2020 | APPLICANT |
| CofO in Progress | 12/8/2020 | ANSON MAGLASANG |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
| CofO Issued | 12/10/2020 | DEROLD HAUFF |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/10/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 3/10/2020 | JUAN ASHTON |
| Construction within easement | Cleared | 6/16/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/12/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/27/2020 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/27/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/27/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/9/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/9/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/9/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 9/9/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/9/2020 | Approved | EUGENE CASSIDY |
| Insulation | 9/14/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/18/2020 | Approved | DAVID FEILER |
| Final | 10/28/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/28/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 10/28/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/28/2020 | Approved | EUGENE CASSIDY |
| Final | 11/13/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/2/2020 | Approved | EUGENE CASSIDY |
| Final | 12/2/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/2/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/2/2020 | Approved | EUGENE CASSIDY |