801 E 118TH ST 90059

Certificate Information: 801 E 118TH ST 90059

Application / Permit
20014-10000-01032
Plan Check / Job No.
B20LA04457
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION OF RECREATION ROOM WITH HALF BATH TO EXISTING GARAGE.
Permit Issued
Issued on 7/22/2020
Issuing Office
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 MONICA RAMIREZ
Corrections Issued 3/5/2020 MONICA RAMIREZ
Plan Check Approved 7/8/2020 RICARDO RAMIREZ
Issued 7/22/2020 APPLICANT
Building Plans Picked Up 7/23/2020 APPLICANT
CofO in Progress 12/8/2020 ANSON MAGLASANG
Permit Finaled 12/10/2020 DEROLD HAUFF
CofO Issued 12/10/2020 DEROLD HAUFF
Permit Finaled 12/10/2020 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2020 JUAN ASHTON
Sewer availability Cleared 3/10/2020 JUAN ASHTON
Construction within easement Cleared 6/16/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 6/26/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/12/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/27/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/27/2020 Approved EUGENE CASSIDY
Green Building Rough 8/27/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/27/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 9/9/2020 Approved EUGENE CASSIDY
Green Building Rough 9/9/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/9/2020 Approved EUGENE CASSIDY
MERV13>=Rough 9/9/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 9/9/2020 Approved EUGENE CASSIDY
Insulation 9/14/2020 Approved EUGENE CASSIDY
Drywall Nailing 9/18/2020 Approved DAVID FEILER
Final 10/28/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 10/28/2020 Approved EUGENE CASSIDY
MERV13>=Final 10/28/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/28/2020 Approved EUGENE CASSIDY
Final 11/13/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 12/2/2020 Approved EUGENE CASSIDY
Final 12/2/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/2/2020 Approved EUGENE CASSIDY
PLUMBING-Final 12/2/2020 Approved EUGENE CASSIDY