1501 W 187TH ST 90248
Certificate Information: 1501 W 187TH ST 90248
- Application / Permit
- 20014-10000-01028
- Plan Check / Job No.
- B20LA04442
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- STORAGE ADDITION TO EXISTING GARAGE PER WFPP.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2020 | ADAM HEGAZI |
| Corrections Issued | 3/9/2020 | ADAM HEGAZI |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Plan Check Approved | 9/15/2020 | ADAM HEGAZI |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 2/8/2022 | EUGENE CASSIDY |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/2/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/30/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 2/8/2021 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/12/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/25/2021 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Rough | 3/25/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/5/2021 | Partial Approval | JOHN KLARIN |
| Deputy Wood Construction | 4/5/2021 | No Result Entered | MARK HATFIELD |
| ELECTRICAL-Rough | 4/5/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 4/5/2021 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 4/5/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/14/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/14/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/14/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 4/14/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 4/14/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/14/2021 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 4/21/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 9/1/2021 | Corrections Issued | JOHN KLARIN |
| Final | 9/1/2021 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 9/1/2021 | Approved | JOHN KLARIN |
| MERV13>=Final | 9/1/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 9/1/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 9/1/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 10/19/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/19/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 10/19/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/19/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/7/2022 | Approved | EUGENE CASSIDY |
| Final | 2/7/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/7/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/7/2022 | Approved | EUGENE CASSIDY |