5144 E ITHACA AVE 90032

Certificate Information: 5144 E ITHACA AVE 90032

Application / Permit
20014-10000-00984
Plan Check / Job No.
B20LA04271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new 2 story ADU per LAMC 12.22 A.33 with attached 4 car garage
Permit Issued
Issued on 9/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 MONICA RAMIREZ
Corrections Issued 4/3/2020 MONICA RAMIREZ
Quality Review Completed 4/9/2020 STANLEY RAAP
Green Plans Picked Up 6/16/2020 APPLICANT
Applicant returned to address corrections 8/18/2020 MONICA RAMIREZ
Building Plans Picked Up 8/21/2020 APPLICANT
Applicant returned to address corrections 10/28/2020 MONICA RAMIREZ
Plan Check Approved 8/15/2022 ARSALAN SHABESTARI
Issued 9/7/2022 APPLICANT
CofO in Progress 4/10/2024 JOSEPH MCGARRY
CofO in Progress 4/12/2024 LILIANA PORTILLO
Permit Finaled 4/13/2024 DEROLD HAUFF
Permit Finaled 4/13/2024 DEROLD HAUFF
CofO Issued 4/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 6/14/2020 KHEDER ALRAZAA
Address approval Cleared 11/19/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 11/19/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/20/2020 CECILIO NAVARRO
Sewer availability Cleared 11/20/2020 CECILIO NAVARRO
Construction near power lines Cleared 2/12/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 11/10/2021 PATRICK MISCHLICH
Hydrant and Access approval Cleared 1/26/2022 KURT CORRAL
"D" conditions Cleared 2/17/2022 YINGSHI HUANG
"Q" conditions Cleared 2/17/2022 YINGSHI HUANG
ZI Cleared 2/17/2022 YINGSHI HUANG
Low Impact Development Cleared 7/13/2022 MARCO SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Dan; Lic. No.: C47140 21121 E SNOW CREEK DR      WALNUT, CA 91789

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/8/2022 Corrections Issued AMY COLIN
PLUMBING-Rough 12/8/2022 Partial Approval AMY COLIN
Sewer 12/8/2022 Approved AMY COLIN
Footing/Foundation/Slab 12/15/2022 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 12/20/2022 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 12/28/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 1/24/2023 Corrections Issued AMY COLIN
Green Building Rough 1/24/2023 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 1/24/2023 Not Ready for Inspection AMY COLIN
Gas Test 2/1/2023 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 6/14/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 6/14/2023 Corrections Issued AMY COLIN
PLUMBING-Rough 6/14/2023 Approved AMY COLIN
HVAC-Rough 6/21/2023 Approved AMY COLIN
BUILDING-Rough-Frame 6/26/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Partial Approval AMY COLIN
Interior/Exterior Lathing 7/3/2023 Partial Approval AMY COLIN
Insulation 7/10/2023 Approved AMY COLIN
Interior/Exterior Lathing 7/10/2023 Partial Approval AMY COLIN
Drywall Nailing 7/17/2023 Approved AMY COLIN
Interior/Exterior Lathing 7/17/2023 Approved AMY COLIN
Shower Pan 7/17/2023 Approved AMY COLIN
BUILDING-Rough-Frame 10/3/2023 Approved AMY COLIN
ELECTRICAL-Final 10/3/2023 Corrections Issued AMY COLIN
Final 10/3/2023 Not Ready for Inspection AMY COLIN
Green Building Final 10/3/2023 Approved AMY COLIN
Green Building Rough 10/3/2023 Approved AMY COLIN
HVAC-Final 10/3/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Final 10/3/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Not Ready AMY COLIN
Service/Power Release 10/3/2023 Not Ready for Inspection AMY COLIN
Smoke Detectors 10/3/2023 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 10/3/2023 Approved AMY COLIN
Final 11/2/2023 Corrections Issued AMY COLIN
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready AMY COLIN
Service/Power Release 11/2/2023 Not Ready for Inspection AMY COLIN
Smoke Detectors 11/2/2023 Corrections Issued AMY COLIN
Final 11/6/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 11/6/2023 SGSOV Not Ready AMY COLIN
Service/Power Release 11/6/2023 Approved AMY COLIN
Smoke Detectors 11/6/2023 Approved AMY COLIN
PLUMBING-Final 11/13/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Gas Test 12/19/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved AMY COLIN
Final 2/9/2024 Corrections Issued JOAQUIN GREENOUGH
Final 4/3/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Final 4/5/2024 OK to Issue CofO JOSEPH MCGARRY
Final 4/11/2024 OK to Issue CofO LILIANA PORTILLO