3721 W REVERE AVE 90039

Certificate Information: 3721 W REVERE AVE 90039

Application / Permit
20014-10000-00976
Plan Check / Job No.
B20LA04241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'x17' ADDITION AND 11.5' x 11' ENCLOSE PATIO TO EXISTING SFD
Permit Issued
Issued on 8/14/2020
Issuing Office
Current Status
CofO Issued on 8/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/3/2020 FERNANDO FLORES
Corrections Issued 3/3/2020 FERNANDO FLORES
Applicant returned to address corrections 7/26/2020 STARR CHEN
Plan Check Approved 8/14/2020 STARR CHEN
Issued 8/14/2020 APPLICANT
CofO in Progress 8/18/2023 HAMIK HARTOUNIAN
Permit Finaled 8/18/2023 RONALD MYRICK
Permit Finaled 8/18/2023 RONALD MYRICK
CofO Issued 8/18/2023 RONALD MYRICK

Permit Application Clearance Information

ZI Cleared 3/3/2020 KENTON TRINH
Low Impact Development Cleared 7/8/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 8/5/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/5/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Mutka,, Jason Richard; Lic. No.: C72255 PO BOX 77144      CORONA, CA 92877

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/14/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 9/23/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 9/23/2020 Conditional Approval HAMIK HARTOUNIAN
Insulation 9/24/2020 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 10/2/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 10/6/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/14/2020 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 10/14/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/14/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/14/2020 Approved HAMIK HARTOUNIAN
Shower Pan 10/14/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/16/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/16/2020 Approved HAMIK HARTOUNIAN
Insulation 10/16/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/16/2020 Approved HAMIK HARTOUNIAN
Wood Frame 10/16/2020 Conditional Approval HAMIK HARTOUNIAN
Insulation 10/19/2020 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 10/22/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/23/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/23/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 8/23/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 8/23/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/15/2022 Corrections Issued HAMIK HARTOUNIAN
Final 9/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 9/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 9/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Final 3/13/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 3/13/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/5/2023 Approved HAMIK HARTOUNIAN
Final 7/5/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/5/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 7/5/2023 Corrections Issued HAMIK HARTOUNIAN
Final 8/17/2023 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 8/17/2023 Approved HAMIK HARTOUNIAN