1707 W 62ND ST 90047

Certificate Information: 1707 W 62ND ST 90047

Application / Permit
20014-10000-00948
Plan Check / Job No.
B20LA04123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION.
Permit Issued
Issued on 3/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Assigned to Plan Check Engineer 3/2/2020 GEORGE ALVAREZ
Corrections Issued 3/2/2020 GEORGE ALVAREZ
Plan Check Approved 3/2/2020 CRISTINA SALAZAR
Issued 3/2/2020 LADBS
CofO in Progress 7/10/2020 FREDDIE RIVERA
Permit Finaled 7/31/2020 DEROLD HAUFF
CofO Issued 7/31/2020 DEROLD HAUFF
Permit Finaled 7/31/2020 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 3/2/2020 ANACANY HURTADO
Address approval Cleared 3/2/2020 WALLIE JONG
Address approval Cleared 3/2/2020 WALLIE JONG
Community Plan Implem. Overlay Cleared 3/2/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 3/2/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 3/2/2020 WALLIE JONG
Sewer availability Cleared 3/2/2020 WALLIE JONG
Tenant Habitability Plan Cleared 3/2/2020 STEVEN HOFSTAD

Contact Information

Contractor Franklin Lincoln Construction Inc; Lic. No.: 1044941-B P O BOX 49750      LOS ANGELES, CA 90049
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2020 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/26/2020 Corrections Issued COREY HUPP
PLUMBING-Rough 3/26/2020 Partial Approval COREY HUPP
Footing/Foundation/Slab 4/1/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 4/1/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Approved FREDDIE RIVERA
Green Building Rough 4/27/2020 Not Ready for Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 4/28/2020 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 5/1/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/4/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/4/2020 Approved FREDDIE RIVERA
Green Building Rough 5/4/2020 Approved FREDDIE RIVERA
HVAC-Rough 5/4/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/4/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 5/5/2020 Approved SABAS ALONSO
ELECTRICAL-Rough 5/5/2020 Approved SABAS ALONSO
Green Building Rough 5/5/2020 Approved SABAS ALONSO
HVAC-Rough 5/5/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/5/2020 Partial Approval SABAS ALONSO
Special/Order Compliance 5/5/2020 Corrections Issued SABAS ALONSO
Insulation 5/6/2020 Approved FREDDIE RIVERA
Drywall Nailing 5/12/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 5/12/2020 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 5/14/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/18/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 5/18/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 7/1/2020 Approved FREDDIE RIVERA
Final 7/1/2020 Corrections Issued FREDDIE RIVERA
Gas Test 7/1/2020 Approved FREDDIE RIVERA
Green Building Final 7/1/2020 Approved FREDDIE RIVERA
HVAC-Final 7/1/2020 Approved FREDDIE RIVERA
PLUMBING-Final 7/1/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Approved FREDDIE RIVERA
Service/Power Release 7/1/2020 Approved FREDDIE RIVERA
Smoke Detectors 7/1/2020 Approved FREDDIE RIVERA
Final 7/9/2020 OK to Issue CofO FREDDIE RIVERA