838-838 1/2 W 65TH ST 90044
Certificate Information: 838-838 1/2 W 65TH ST 90044
- Application / Permit
- 20014-10000-00915
- Plan Check / Job No.
- B20LA04010
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Addition of ADU in between 2 (E) single family dwellings. conerting to a duplex with attached ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- CofO Issued on 11/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | SHANGQIN XIE |
| Corrections Issued | 3/18/2020 | SHANGQIN XIE |
| Quality Review Completed | 3/26/2020 | STANLEY RAAP |
| Green Plans Picked Up | 3/31/2020 | APPLICANT |
| Applicant returned to address corrections | 11/2/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/16/2021 | SHANGQIN XIE |
| Plan Check Approved | 12/20/2021 | SHANGQIN XIE |
| Issued | 2/28/2022 | APPLICANT |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| Refund in Progress | 5/20/2025 | SELENIA GARCIA |
| Refund Denied | 6/19/2025 | EMMA PANGILINAN |
| Issued | 6/19/2025 | EMMA PANGILINAN |
| CofO in Progress | 11/13/2025 | BARRY HACHE |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
| CofO Issued | 11/16/2025 | DEROLD HAUFF |
| Permit Finaled | 11/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 12/17/2020 | SARAHI ORTEGA |
| Address approval | Cleared | 12/23/2020 | WALLIE JONG |
| Sewer availability | Cleared | 12/23/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2022 | No Access for Inspection | SHAVONNE ESPINOZA |
| Pre-Inspection | 9/4/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 11/4/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 11/4/2025 | Approved | BARRY HACHE |
| Final | 11/4/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 11/4/2025 | Approved | BARRY HACHE |
| Green Building Final | 11/4/2025 | Approved | BARRY HACHE |
| Green Building Rough | 11/4/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 11/4/2025 | Approved | BARRY HACHE |
| Final | 11/13/2025 | OK to Issue CofO | BARRY HACHE |