- SUPPLEMENTAL TO PERMOIT # 18010-10000-00248: CHANGE OF USE OF (E) 6TH FLOOR PARKING TO MEDIA PRODUCTION & INFILL (E) 6TH FLOOR RAMP OPENING & INSTALL NEW STAIRS & CHANGE OF EXTERIOR FINSHES & INTERIR LAYOUT CHANGES.
- Permit Issued
- Issued on 10/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | GARO TELMI |
| Corrections Issued | 3/23/2020 | GARO TELMI |
| Quality Review Completed | 3/23/2020 | KEN GILL |
| Building Plans Picked Up | 3/24/2020 | APPLICANT |
| Applicant returned to address corrections | 5/12/2020 | GARO TELMI |
| Disabled Access Plans Picked Up | 5/15/2020 | APPLICANT |
| Green Plans Picked Up | 7/16/2020 | APPLICANT |
| Applicant returned to address corrections | 9/8/2020 | GARO TELMI |
| Plan Check Approved | 10/7/2020 | GARO TELMI |
| Issued | 10/16/2020 | APPLICANT |
| CofO in Progress | 8/12/2021 | EDWIN GREGORYONA |
| Permit Finaled | 8/16/2021 | ERNESTO CORRAL |
| CofO Issued | 8/16/2021 | ERNESTO CORRAL |
| Permit Finaled | 8/16/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 3/27/2020 | CECILIO NAVARRO |
| Internal circulation | Cleared | 3/27/2020 | MOHAMMAD HASAN |
| Transportation Demand Ord. | Cleared | 3/27/2020 | MOHAMMAD HASAN |
| Address approval | Cleared | 4/1/2020 | CECILIO NAVARRO |
| Building over 3-story or 36-ft | Cleared | 4/1/2020 | CALOSHA APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 4/1/2020 | DOMINIQUE MEDINA |
| Hydrant and Access approval | Cleared | 4/2/2020 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | PAMELA TENEZA |
| Low Impact Development | Cleared | 6/30/2020 | MITESH PATEL |
| Green Code | Cleared | 7/16/2020 | GARO TELMI |
| Sewer availability | Cleared | 7/29/2020 | PAMELA TENEZA |
| Site Plan review | Cleared | 9/1/2020 | JOE LUCKEY |
| ZA Case | Cleared | 9/1/2020 | JOE LUCKEY |
| ZI | Cleared | 9/1/2020 | JOE LUCKEY |
| DAS Clearance | Cleared | 10/2/2020 | GARO TELMI |
Contact Information
| Architect | Teiger, Douglas Haupt; Lic. No.: C20505 | 8924 LINDBLADE STREET CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
| Engineer | Berliner, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/7/2021 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/8/2021 | Approved | TIMOTHY BUXTON |
| Green Building Final | 6/8/2021 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 6/8/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 6/8/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 6/8/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 6/8/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 6/8/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 6/8/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 6/8/2021 | Approved | TIMOTHY BUXTON |
| Final | 8/12/2021 | OK to Issue CofO | EDWIN GREGORYONA |