910 S MASSELIN AVE 90036
Certificate Information: 910 S MASSELIN AVE 90036
- Application / Permit
- 20014-10000-00893
- Plan Check / Job No.
- B20LA03921
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (7'-5" X 18'-2") TO REAR AND ADDITION (2'-0" X 4'-4") TO SIDE OF (E) SFD
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/10/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/13/2020 | FERNANDO FLORES |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 11/2/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 11/2/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/27/2020 | JEANETTE VONG |
| HPOZ | Cleared | 3/13/2020 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/20/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 4/24/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/29/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 4/29/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 4/29/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/11/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 5/27/2020 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 6/29/2020 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/1/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 7/1/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 7/1/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/14/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/14/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 7/14/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/14/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 8/4/2020 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 8/4/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/12/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/28/2020 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 8/28/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 9/28/2020 | Approved | ARTHUR SARGSYAN |
| Final | 10/22/2020 | OK to Issue CofO | ARTHUR SARGSYAN |
| Green Building Final | 10/22/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 10/22/2020 | Approved | ARTHUR SARGSYAN |