2142 N EASTERN AVE 90032
Certificate Information: 2142 N EASTERN AVE 90032
- Application / Permit
- 20014-10000-00889
- Plan Check / Job No.
- B20LA03916
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1200SQ.FT A.D.U. ADDITION TO (E) DETACHED GARAGE AT REAR PER ORDINANCE # 186481
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | RAHEL BEYENE |
| Corrections Issued | 3/25/2020 | RAHEL BEYENE |
| Quality Review Completed | 4/2/2020 | STANLEY RAAP |
| Green Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/30/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 1/13/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 2/26/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/5/2021 | RAHEL BEYENE |
| Plan Check Approved | 3/16/2021 | RAHEL BEYENE |
| Issued | 6/16/2021 | APPLICANT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| CofO in Progress | 6/17/2022 | AMY COLIN |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
| CofO Issued | 6/18/2022 | DEROLD HAUFF |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/15/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 9/10/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/11/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 12/23/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/5/2021 | RAHEL BEYENE |
| Green Code | Cleared | 1/13/2021 | VIVIAN LAO |
| Low Impact Development | Cleared | 2/16/2021 | SARAH YOUSSEF |
| DPI Written Notices | Cleared | 3/5/2021 | RAHEL BEYENE |
| Roof/Waste drainage to street | Cleared | 3/8/2021 | WALLIE JONG |
Contact Information
| Contractor | Pang Hometeam Inc; Lic. No.: 1051817-B | 15111 ANOLA STREET WHITTIER, CA 90604 |
| Engineer | Li,, Edward Guojun; Lic. No.: C56706 | 1107 FAIR OAKS AVE 118 SOUTH PASADENA, CA 91030 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/6/2021 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 10/7/2021 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | COREY HUPP |
| Sewer | 11/1/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | COREY HUPP |
| Insulation | 11/4/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 1/10/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 1/10/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/10/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/14/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 1/14/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 1/24/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/24/2022 | Partial Approval | OSVALDO PARAMO |
| Insulation | 1/26/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 2/3/2022 | Approved | RUBEN SALAS |
| Service/Power Release | 3/10/2022 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Final | 4/28/2022 | Approved | AMY COLIN |
| Final | 4/28/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 4/28/2022 | Approved | AMY COLIN |
| Gas Test | 4/28/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 4/28/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 4/28/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 4/28/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 4/28/2022 | Approved | AMY COLIN |
| Gas Test | 5/3/2022 | Approved | AMY COLIN |
| Service/Power Release | 5/3/2022 | Approved | AMY COLIN |
| Final | 6/17/2022 | OK to Issue CofO | AMY COLIN |
| Green Building Final | 6/17/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | AMY COLIN |