8911 W GIBSON ST 90034
Certificate Information: 8911 W GIBSON ST 90034
- Application / Permit
- 20014-10000-00879
- Plan Check / Job No.
- B20LA03899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADITION TO SFD TO ADD A MASTER BEDROOM SUITE AND REMODEL KITCHEN AREA
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2020 | MONICA RAMIREZ |
| Corrections Issued | 3/9/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/7/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/16/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 4/19/2021 | FARSHAD ALIMOHAMADI |
| Issued | 4/21/2021 | APPLICANT |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | EVAN COOPER |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
| CofO Issued | 10/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 3/9/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 2/10/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/18/2021 | ROSA SILVA |
Contact Information
| Contractor | A N R Roofing; Lic. No.: 874964-B | 4743 EAGLE ROCK BLVD LOS ANGELES, CA 90041 |
| Engineer | Guzman,, Jesus Enrique; Lic. No.: C27906 | 927 AMELUXEN AVE HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 7/1/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/16/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/27/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 8/27/2021 | Approved | EVAN COOPER |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 8/27/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 8/27/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/2/2021 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | EVAN COOPER |
| Green Building Rough | 9/8/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 9/8/2021 | Partial Approval | EVAN COOPER |
| Insulation | 9/8/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 9/13/2021 | Approved | EVAN COOPER |
| Shower Pan | 9/17/2021 | Partial Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 9/24/2021 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/24/2021 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/13/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 12/13/2021 | Conditional Approval | EVAN COOPER |
| Wood Frame | 12/13/2021 | Conditional Approval | EVAN COOPER |
| Final | 4/1/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 4/1/2022 | Approved | EVAN COOPER |
| Green Building Final | 4/1/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/1/2022 | Approved | EVAN COOPER |
| Final | 4/13/2022 | Corrections Issued | EVAN COOPER |
| Final | 9/27/2022 | OK to Issue CofO | EVAN COOPER |