912 S MASSELIN AVE 90036
Certificate Information: 912 S MASSELIN AVE 90036
- Application / Permit
- 20014-10000-00873
- Plan Check / Job No.
- B20LA03848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to (E) detached garage and conversion of entire building into an Accessory Dwelling Unit. Detached ADU per ordinance.
- Permit Issued
- Issued on 9/15/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | HELEN NGUYEN |
| Corrections Issued | 3/4/2020 | HELEN NGUYEN |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/24/2020 | HELEN NGUYEN |
| Plan Check Approved | 9/14/2020 | HELEN NGUYEN |
| Issued | 9/15/2020 | APPLICANT |
| CofO in Progress | 9/16/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 9/20/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
| CofO Issued | 9/22/2021 | DEROLD HAUFF |
| Permit Finaled | 9/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/25/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/5/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 6/8/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/8/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | WALLIE JONG |
| Sewer availability | Cleared | 6/15/2020 | WALLIE JONG |
| HPOZ | Cleared | 8/4/2020 | CHRISTINA PARK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2020 | Approved | JOSEPH MCGARRY |
| Grading Pre-Inspection | 1/11/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 1/20/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/9/2021 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 2/9/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 2/9/2021 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 2/24/2021 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/4/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/16/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 4/27/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 4/27/2021 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Rough | 4/27/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/27/2021 | Approved | JOSEPH MCGARRY |
| Structural Steel Frame | 4/27/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/7/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/7/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 5/7/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/7/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 5/7/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/18/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/26/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 7/30/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| Final | 9/3/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 9/3/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 9/3/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Smoke Detectors | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| Final | 9/10/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Final | 9/16/2021 | OK to Issue CofO | ARTHUR SARGSYAN |