2228 N MEADOWVALE AVE 90031
Certificate Information: 2228 N MEADOWVALE AVE 90031
- Application / Permit
- 20014-10000-00845
- Plan Check / Job No.
- B20LA03725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION WITH ROOF DECK TO (E) SINGLE FAMILY DWELLING AT REAR.
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2020 | KEVIN MORALES |
| Corrections Issued | 2/25/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 9/25/2020 | RAHEL BEYENE |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Plan Check Approved | 2/9/2021 | FARSHAD ALIMOHAMADI |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 2/8/2023 | KATHRYN BUTTERWORTH |
| CofO Issued | 2/15/2023 | DEROLD HAUFF |
| Permit Finaled | 2/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 2/25/2020 | ERIK BEASLEY |
| ZI | Cleared | 2/25/2020 | TERRI OSBORNE |
Contact Information
| Contractor | D C L A Design Build Inc; Lic. No.: 1060451-B | 712 N BONNIE BRAE ST LOS ANGELES, CA 90026 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 900 N SANTA ANITA AVE STE B ARCADIA, CA 91006 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/18/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/20/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 8/1/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/23/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 8/23/2022 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 8/23/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/23/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/30/2022 | Conditional Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 9/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/7/2022 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 9/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 9/21/2022 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/21/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 9/21/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | THOMAS LOGRASSO |
| Final | 1/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/19/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 1/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 1/19/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 1/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 1/19/2023 | Approved | THOMAS LOGRASSO |
| Final | 1/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 1/25/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 1/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 1/30/2023 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| MERV13>=Final | 1/30/2023 | Approved | KATHRYN BUTTERWORTH |