3915 N COLLIS AVE 90032
Certificate Information: 3915 N COLLIS AVE 90032
- Application / Permit
- 20014-10000-00844
- Plan Check / Job No.
- B20LA03716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING TWO CAR GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT AND ADDITION OF RECREATION ROOM AT REAR OF STRUCTURE.
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 8/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | RICARDO RAMIREZ |
| Corrections Issued | 3/26/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 9/2/2020 | TSE MING HUANG |
| Green Plans Picked Up | 9/11/2020 | APPLICANT |
| Plan Check Approved | 9/16/2020 | SHANGQIN XIE |
| Issued | 9/17/2020 | APPLICANT |
| Building Plans Picked Up | 9/21/2020 | APPLICANT |
| CofO in Progress | 7/21/2021 | COREY HUPP |
| CofO in Progress | 7/21/2021 | COREY HUPP |
| Permit Finaled | 8/17/2021 | DEROLD HAUFF |
| CofO Issued | 8/17/2021 | DEROLD HAUFF |
| Permit Finaled | 8/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/18/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/18/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 5/18/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 5/18/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/15/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 6/15/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/23/2020 | PATRICK MISCHLICH |
| "D" conditions | Cleared | 6/24/2020 | JASON CHAN |
| "Q" conditions | Cleared | 6/24/2020 | JASON CHAN |
| Disturb/Remove Protected Trees | Cleared | 7/8/2020 | STEPHEN DUPREY |
| Green Code | Cleared | 9/9/2020 | VIVIAN LAO |
| GPI Written Notices | Cleared | 9/16/2020 | RICARDO RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/2/2020 | Approved | OSVALDO PARAMO |
| Pre-Inspection | 10/16/2020 | Partial Inspection | COREY HUPP |
| Pre-Inspection | 11/23/2020 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 2/18/2021 | Approved | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 3/18/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 3/30/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/30/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/30/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 3/30/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/12/2021 | Corrections Issued | RUBEN SALAS |
| Interior/Exterior Lathing | 4/12/2021 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 6/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/8/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 6/8/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 6/8/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 6/24/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 6/24/2021 | Approved | COREY HUPP |
| Final | 7/20/2021 | OK to Issue CofO | COREY HUPP |