5630 W HILL OAK DR 90068
Certificate Information: 5630 W HILL OAK DR 90068
- Application / Permit
- 20014-10000-00799
- Plan Check / Job No.
- B20LA03490
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EMODEL OF EXISTING 2 STORY (3 BEDROOMS & 21/2 BATHROOMS) SINGLE FAMILY DWELLING TO HAVE 3 BEDROOMS AND 31/2 BATHROOMS. ADDITION OF (12'-11" x 16'-11") IRREGULAR SHAPE. @ SECOND FLOOR AREA AT THE REAR OF THE HOUSE. REMODEL OF EXISTING KITCHEN. REPLACEMENT OF DOORS AND WINDOWS. DEMOLITION OF EXISTING CANTILEVERED DECK @ REAR OF THE HOUSE. PROPOSED CANTILEVERED DECK @ REAR OF THE HOUSE. NEW STUCCO FINISH, WOOD COMPOSITE SIDING ON THE BUILDING FACADE, REMOVAL OF FENCE IN FRONT AND SIDE YARDS FOR NEW 6-FT WOOD FENCE IN THE SIDE YARD, REMOVAL OF FRONT PORCH AND WALKWAY FOR A NEW FRONT WALKWAY AND PLANTER BOX.
- Permit Issued
- Issued on 5/18/2020
- Issuing Office
- Current Status
- CofO Issued on 11/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/17/2020 | FARSHAD ALIMOHAMADI |
| Green Plans Picked Up | 3/20/2020 | APPLICANT |
| Quality Review Completed | 3/22/2020 | YOUNG KIM |
| Plan Check Approved | 5/18/2020 | FARSHAD ALIMOHAMADI |
| Issued | 5/18/2020 | APPLICANT |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| CofO in Progress | 10/29/2020 | BRIAN SULLIVAN |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
| CofO Issued | 11/5/2020 | DEROLD HAUFF |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 3/26/2020 | HERMINIGILDO AGUSTIN |
| Sewer availability | Cleared | 4/9/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 4/13/2020 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 4/17/2020 | KIRK LINKLATER |
| "D" conditions | Cleared | 5/11/2020 | LIKYELESH ABERA |
| ZI | Cleared | 5/11/2020 | LIKYELESH ABERA |
| Green Code | Cleared | 5/14/2020 | FARSHAD ALIMOHAMADI |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 3332 BENNETT DRIVE LOS ANGELES, CA 90068 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/3/2020 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 6/16/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/23/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/23/2020 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/23/2020 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 6/23/2020 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 6/23/2020 | Partial Approval | BRIAN SULLIVAN |
| Structural Steel Frame | 6/23/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/26/2020 | Approved | BRIAN SULLIVAN |
| Wood Frame | 6/26/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/6/2020 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/6/2020 | Partial Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 7/9/2020 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/10/2020 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 7/10/2020 | Approved | BRIAN SULLIVAN |
| Deputy Steel/Welding | 7/13/2020 | Conditional Approval | ROBERT CORNELL |
| Deputy Steel/Welding | 7/14/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 7/16/2020 | Conditional Approval | ROBERT CORNELL |
| Deputy Steel/Welding | 7/17/2020 | Conditional Approval | ROBERT CORNELL |
| Drywall Nailing | 7/20/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 7/20/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/20/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/20/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/26/2020 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/26/2020 | Approved | BRIAN SULLIVAN |
| Green Building Final | 10/26/2020 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 10/26/2020 | Approved | BRIAN SULLIVAN |
| Final | 10/29/2020 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2020 | SGSOV Approved | BRIAN SULLIVAN |