1014 S MALGREN AVE 90732

Certificate Information: 1014 S MALGREN AVE 90732

Application / Permit
20014-10000-00796
Plan Check / Job No.
B20LA03464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY ADDITION TO (E) S.F.D AND INTERIOR REMODEL. WORK INCLUDES REMODEL OF KITCHEN, BATHROOM AND MASTER BATH ROOM.
Permit Issued
Issued on 6/10/2020
Issuing Office
Current Status
CofO Issued on 8/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/21/2020 RAHEL BEYENE
Corrections Issued 2/21/2020 RAHEL BEYENE
Plan Check Approved 3/18/2020 FERNANDO FLORES
Issued 6/10/2020 APPLICANT
CofO in Progress 8/3/2021 ANSON MAGLASANG
Permit Finaled 8/4/2021 DEROLD HAUFF
CofO Issued 8/4/2021 DEROLD HAUFF
Permit Finaled 8/4/2021 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 2/21/2020 RAHEL BEYENE
Grading Pre-Inspection Cleared 2/21/2020 RAHEL BEYENE
Eng Process Fee Ord 176,300 Cleared 2/26/2020 YEGANEH SADEGHI
Roof/Waste drainage to street Cleared 2/26/2020 YEGANEH SADEGHI
Sewer availability Cleared 2/26/2020 YEGANEH SADEGHI
Miscellaneous Cleared 3/2/2020 PABLO ESTRADA

Contact Information

Contractor Cook James Iii - General Contractor; Lic. No.: 550563-B P O BOX 3412      MANHATTAN BEACH, CA 90266
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/6/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 7/6/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/13/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 7/13/2020 Not Ready for Inspection JOHN KLARIN
Wood Frame 7/13/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 7/16/2020 Corrections Issued JOHN KLARIN
Insulation 7/16/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 7/16/2020 Conditional Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 9/18/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 9/18/2020 Approved JOHN KLARIN
Green Building Rough 9/18/2020 Approved JOHN KLARIN
HVAC-Rough 9/18/2020 Approved JOHN KLARIN
PLUMBING-Rough 9/18/2020 Approved JOHN KLARIN
Wood Frame 9/18/2020 Approved JOHN KLARIN
Insulation 9/30/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 9/30/2020 Approved JOHN KLARIN
Drywall Nailing 10/8/2020 Approved JOHN KLARIN
Shower Pan 10/8/2020 Approved JOHN KLARIN
Final 4/20/2021 Corrections Issued JOHN KLARIN
Green Building Final 4/20/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/20/2021 Approved JOHN KLARIN
ELECTRICAL-Final 6/16/2021 Approved JOHN KLARIN
Final 6/16/2021 Corrections Issued JOHN KLARIN
Green Building Final 6/16/2021 Approved JOHN KLARIN
HVAC-Final 6/16/2021 Corrections Issued JOHN KLARIN
PLUMBING-Final 6/16/2021 Approved JOHN KLARIN
Final 7/13/2021 Corrections Issued JOHN KLARIN
Final 8/3/2021 OK to Issue CofO ANSON MAGLASANG