2126 S PELHAM AVE 90025

Certificate Information: 2126 S PELHAM AVE 90025

Application / Permit
20014-10000-00762
Plan Check / Job No.
B20LA03270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
First and second floor addition to (E) SFD, including remodel (E) first floor. Fire sprinkler is provided throughout building.
Permit Issued
Issued on 8/26/2020
Issuing Office
Current Status
CofO Issued on 4/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 HELEN NGUYEN
Corrections Issued 3/16/2020 HELEN NGUYEN
Quality Review Completed 3/21/2020 YOUNG KIM
Applicant returned to address corrections 4/27/2020 HELEN NGUYEN
Applicant returned to address corrections 5/7/2020 HELEN NGUYEN
Applicant returned to address corrections 7/21/2020 HELEN NGUYEN
Applicant returned to address corrections 7/23/2020 HELEN NGUYEN
Green Plans Picked Up 8/11/2020 APPLICANT
Plan Check Approved 8/18/2020 HELEN NGUYEN
Building Plans Picked Up 8/18/2020 APPLICANT
Issued 8/26/2020 APPLICANT
CofO in Progress 4/20/2022 MICHAEL PELHAM
Permit Finaled 4/20/2022 DANIEL ORRANTE
CofO Issued 4/20/2022 DANIEL ORRANTE
Permit Finaled 4/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/5/2020 ANTHONY MAINEZ
Sewer availability Cleared 5/5/2020 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/29/2020 VASIL MIHALEV
Low Impact Development Cleared 6/17/2020 MARTIN FRAGOSO
Green Code Cleared 7/6/2020 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 7/15/2020 ANTHONY MAINEZ
GPI Written Notices Cleared 7/20/2020 HELEN NGUYEN

Contact Information

Contractor D C L A Design Build Inc; Lic. No.: 1060451-B 712 N BONNIE BRAE ST      LOS ANGELES, CA 90026
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384
Engineer Kaligi,, Sean; Lic. No.: M37797 26905 ROLLING HILLS AVE      SANTA CLARITA, CA 91387
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Geologist Kaligi,, Azad Adam; Lic. No.: GEO9287 26905 ROLLING HILLS AVE      SANTA CLARITA, CA 91387

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/9/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/9/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 10/9/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 10/9/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 10/9/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 10/9/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 10/14/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 10/14/2020 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 10/14/2020 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 10/23/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 10/26/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/26/2020 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 10/28/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 10/29/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 11/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/10/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 11/10/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 11/10/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/16/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 11/16/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 11/16/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 11/25/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 11/25/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/25/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 11/25/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 11/30/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 12/2/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 12/2/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 12/2/2020 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 12/2/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 12/18/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/14/2021 No Access for Inspection MATT KELLERMAN
Wood Frame 1/20/2021 Corrections Issued CHRISTOPHER WILSON
Deputy Wood Construction 1/21/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/22/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 2/3/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 2/10/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/19/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/19/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 4/19/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/21/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/21/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/23/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/23/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/28/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/30/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 5/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 5/6/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 5/6/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 5/13/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 6/18/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/4/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 8/4/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Gas Test 8/12/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/20/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 8/31/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Final 9/2/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 9/2/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 9/14/2021 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 9/14/2021 Approved CARLOS MATAMOROS
Green Building Final 9/14/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/14/2021 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/14/2021 Approved CARLOS MATAMOROS
Final 12/20/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 12/20/2021 Approved BRENDAN LOONEY
Final 2/8/2022 Partial Approval BRENDAN LOONEY
Final 4/20/2022 OK to Issue CofO MICHAEL PELHAM