1432 W 58TH PL 90047
Certificate Information: 1432 W 58TH PL 90047
- Application / Permit
- 20014-10000-00746
- Plan Check / Job No.
- B20LA03176
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION AT THE REAR OF (E) SINGLE FAMILY DWELLING FOR AN ATTACHED ADU. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 8/18/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2020 | KEVIN MORALES |
| Corrections Issued | 2/19/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 4/28/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/23/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 8/10/2020 | AUNG SOE |
| Plan Check Approved | 8/12/2020 | AUNG SOE |
| Issued | 8/18/2020 | APPLICANT |
| Building Plans Picked Up | 8/19/2020 | APPLICANT |
| CofO in Progress | 7/14/2021 | FREDDIE RIVERA |
| Permit Finaled | 8/17/2021 | DEROLD HAUFF |
| CofO Issued | 8/17/2021 | DEROLD HAUFF |
| Permit Finaled | 8/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 6/25/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | THOMAS LANG |
| Sewer availability | Cleared | 6/26/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/27/2020 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/31/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/23/2020 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 9/23/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 9/23/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/23/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/20/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/20/2020 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 10/26/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/26/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/26/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 10/26/2020 | Approved | FREDDIE RIVERA |
| Wood Frame | 10/26/2020 | Approved | FREDDIE RIVERA |
| Insulation | 10/30/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/30/2020 | Conditional Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/5/2020 | Approved | FREDDIE RIVERA |
| Shower Pan | 11/5/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 4/13/2021 | Approved | FREDDIE RIVERA |
| Final | 4/13/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/23/2021 | Approved | FREDDIE RIVERA |
| Final | 4/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 4/23/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/23/2021 | Approved | FREDDIE RIVERA |
| Final | 5/13/2021 | Conditional Approval | FREDDIE RIVERA |