5356 S WEST BLVD 90043
Certificate Information: 5356 S WEST BLVD 90043
- Application / Permit
- 20014-10000-00707
- Plan Check / Job No.
- B20LA03025
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO SINGLE FAMILY TO INCREASE (E) BEDROOM SIZE AND INTERIOR KITCHEN AND BATHROOM REMODEL
- Permit Issued
- Issued on 4/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2020 | FERNANDO FLORES |
| Corrections Issued | 2/18/2020 | FERNANDO FLORES |
| Plan Check Approved | 3/23/2020 | SINA KHOSRAVI |
| Issued | 4/24/2020 | LADBS |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| CofO in Progress | 2/16/2021 | DAVID FEILER |
| Permit Finaled | 2/27/2021 | DEROLD HAUFF |
| CofO Issued | 2/27/2021 | DEROLD HAUFF |
| Permit Finaled | 2/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/19/2020 | JEANIE LAM |
Contact Information
| Contractor | Ortiz Builders Inc; Lic. No.: 952610-B | 8728 ALONDRA BLVD BELLFLOWER, CA 90706 |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/4/2020 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 5/7/2020 | Not Ready for Inspection | COREY HUPP |
| Shower Pan | 5/7/2020 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 5/8/2020 | Approved | COREY HUPP |
| Shower Pan | 5/8/2020 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 5/14/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/14/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/22/2020 | Not Ready for Inspection | COREY HUPP |
| Insulation | 5/22/2020 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 5/22/2020 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 5/27/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 6/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/29/2020 | Approved | COREY HUPP |
| Wood Frame | 6/29/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | COREY HUPP |
| Green Building Rough | 7/2/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 7/2/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 7/7/2020 | Approved | ELMER BLAND |
| Shower Pan | 7/7/2020 | Not Ready for Inspection | ELMER BLAND |
| Shower Pan | 7/9/2020 | Approved | COREY HUPP |
| Insulation | 7/13/2020 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/13/2020 | Not Ready for Inspection | SABAS ALONSO |
| Special/Order Compliance | 7/13/2020 | Approved | SABAS ALONSO |
| Insulation | 7/22/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/22/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/31/2020 | Approved | SABAS ALONSO |
| Special/Order Compliance | 8/10/2020 | OK to Expire Permit | COREY HUPP |
| ELECTRICAL-Final | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| Final | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| Green Building Final | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| HVAC-Final | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Final | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 10/13/2020 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Final | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Footing/Foundation/Slab | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Green Building Final | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Final | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Not Ready | DONALD CRICHLOW |
| Smoke Detectors | 10/22/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Final | 11/5/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 11/5/2020 | Approved | DAVID FEILER |
| Green Building Final | 11/5/2020 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 11/5/2020 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/15/2020 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 12/15/2020 | Approved | DAVID FEILER |
| Final | 1/19/2021 | OK to Issue CofO | DAVID FEILER |
| Service/Power Release | 1/19/2021 | Approved | DAVID FEILER |