3027 N GRACIA ST 90039
Certificate Information: 3027 N GRACIA ST 90039
- Application / Permit
- 20014-10000-00703
- Plan Check / Job No.
- B20LA03005
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BATHROOM ADDITION TO SFD 70 SF AND REMODEL OF EXISTING SINGLE FAMILY TO CONVERT EXISITNG DINING ROOM TO BEDROM
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | MONICA RAMIREZ |
| Corrections Issued | 2/14/2020 | MONICA RAMIREZ |
| Application Withdrawn | 2/14/2020 | APPLICANT |
| Re-Activate Applicaton | 2/14/2020 | APPLICANT |
| Plan Check Approved | 2/27/2020 | MOHAMMAD ESMAILI |
| Issued | 2/27/2020 | LADBS |
| CofO in Progress | 5/12/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/27/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/10/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/10/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/16/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/16/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/16/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/16/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/26/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/26/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/31/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 3/31/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/1/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/1/2020 | Approved | THOMAS LOGRASSO |
| Insulation | 4/7/2020 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 4/7/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/14/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/5/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 5/5/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/5/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/5/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/12/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/12/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 5/12/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/12/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 5/12/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/12/2020 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/12/2020 | Approved | HAMIK HARTOUNIAN |