1724 S OXFORD AVE 90006
Certificate Information: 1724 S OXFORD AVE 90006
- Application / Permit
- 20014-10000-00688
- Plan Check / Job No.
- B20LA02962
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'7" X 25'2" 2-STORY DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 11/3/2020
- Issuing Office
- Current Status
- CofO Issued on 8/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | AMIR DANAI |
| Corrections Issued | 3/24/2020 | AMIR DANAI |
| Quality Review Completed | 4/2/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 4/21/2020 | APPLICANT |
| Green Plans Picked Up | 8/17/2020 | APPLICANT |
| Plan Check Approved | 9/25/2020 | AMIR DANAI |
| Issued | 11/3/2020 | APPLICANT |
| CofO in Progress | 7/19/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
| CofO Issued | 8/4/2021 | DEROLD HAUFF |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/3/2020 | VIVIAN LAO |
| Address approval | Cleared | 4/24/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 5/22/2020 | GEORGE SUCHAND |
| HPOZ | Cleared | 7/20/2020 | DEEPEAKA DHALIWAL |
| Roof/Waste drainage to street | Cleared | 9/1/2020 | JAMES KHO |
| Low Impact Development | Cleared | 10/19/2020 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 10/28/2020 | PAMELA TENEZA |
Contact Information
| Contractor | Tis, Inc.; Lic. No.: 865091-B | 29320 LAS TERRENO LANE VALENCIA, CA 91354 |
| Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Pre-Inspection | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 11/19/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/14/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/14/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 12/14/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 1/7/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 1/19/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 1/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/28/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/28/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/28/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/28/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 1/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 2/12/2021 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/22/2021 | Partial Approval | ROBERT VORHIS |
| Insulation | 2/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/3/2021 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 3/3/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 3/15/2021 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 4/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 4/30/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 4/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 4/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 4/30/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 5/10/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 5/21/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Gas Test | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 5/21/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 5/21/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/7/2021 | Partial Inspection | RUBEN SALAS |
| Final | 6/9/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 7/19/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |