3615 N LONGRIDGE AVE 91423

Certificate Information: 3615 N LONGRIDGE AVE 91423

Application / Permit
20014-10000-00672
Plan Check / Job No.
B20LA02877
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTERIOR REMODEL, INTERIOR REMODEL, AND ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/5/2023
Issuing Office
Valley
Current Status
Issued on 12/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Green Plans Picked Up 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 FERNANDO FLORES
Corrections Issued 3/9/2020 FERNANDO FLORES
Quality Review Completed 3/14/2020 STANLEY RAAP
Building Plans Picked Up 3/18/2020 APPLICANT
Plan Check Approved 11/30/2023 DANIEL YIP
Issued 12/5/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/26/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/26/2023 ROMAN GUTIERREZ
Address approval Cleared 7/27/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/27/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/27/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/27/2023 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/27/2023 ROMAN GUTIERREZ
Sewer availability Cleared 7/27/2023 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 8/3/2023 LAVEON RIDER
Low Impact Development Cleared 8/9/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 8/14/2023 MARKOS PEREZ-BRAN
Miscellaneous Cleared 11/28/2023 BRENNEN OBETO
Specific Plan Cleared 11/28/2023 BRENNEN OBETO
GPI Written Notices Cleared 11/30/2023 FERNANDO FLORES
Grading Pre-Inspection Cleared 11/30/2023 FERNANDO FLORES
Green Code Cleared 11/30/2023 VIVIAN LAO
Zoning Information File Cleared 11/30/2023 FERNANDO FLORES

Contact Information

Architect Hsu,, Peggy P; Lic. No.: C32998 3708 BEVERLY RIDGE DR.      SHERMAN OAKS, CA 91423
Contractor L A Build Corp; Lic. No.: 893881-B 21022 VICTORY BLVD      WOODLAND HILLS, CA 91367
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 2/14/2024 Conditional Approval ROBERT GOLD
Deputy Reinf. Concrete 2/15/2024 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/15/2024 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 2/15/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 2/16/2024 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 2/21/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 2/21/2024 Partial Inspection CHRISTOPHE COCHRAN
Piling/Pier/Caisson 2/21/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 2/22/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/26/2024 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/26/2024 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 2/26/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 2/27/2024 Conditional Approval JUAN VALENZUELA
Deputy Shotcrete 4/19/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/19/2024 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/19/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/22/2024 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/7/2024 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 5/24/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 5/29/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 5/30/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 6/6/2024 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 6/27/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/23/2024 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/14/2024 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 8/14/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 8/21/2024 Corrections Issued JACK KARGODORIAN
Deputy Reinf. Concrete 8/27/2024 Conditional Approval JUAN VALENZUELA
Sewer 9/6/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Steel/Welding 9/9/2024 Conditional Approval JUAN VALENZUELA
Sewer 9/10/2024 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 9/19/2024 Approved CHRISTOPHE COCHRAN
Sewer 9/26/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 9/26/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 9/26/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/1/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 10/1/2024 Approved CHRISTOPHE COCHRAN
Underground Mechanical 10/1/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 10/21/2024 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 10/21/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/29/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 10/29/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 10/29/2024 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/31/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 10/31/2024 Approved CHRISTOPHE COCHRAN
Insulation 11/5/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 11/22/2024 Approved CHRISTOPHE COCHRAN
Piling/Pier/Caisson 12/18/2025 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/2/2026 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/5/2026 Approved CHRISTOPHE COCHRAN
Gas Test 2/10/2026 Approved CHRISTOPHE COCHRAN
Service/Power Release 2/10/2026 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 2/17/2026 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 2/20/2026 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/24/2026 Partial Inspection MISAEL ESPARZA
Final 2/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Grading Pre-Inspection 2/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 2/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/25/2026 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 2/25/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Approved JAVIER RAMOS JR