21029 W BASSETT ST 91303
Certificate Information: 21029 W BASSETT ST 91303
- Application / Permit
- 20014-10000-00669
- Plan Check / Job No.
- B20LA02863
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED 40' X 19' ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(B).
- Permit Issued
- Issued on 6/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Green Plans Picked Up | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | MICHAEL LOPEZ |
| Corrections Issued | 3/17/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 3/19/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 3/20/2020 | APPLICANT |
| Plan Check Approved | 6/11/2020 | MICHAEL LOPEZ |
| Issued | 6/26/2020 | LADBS |
| CofO in Progress | 12/31/2020 | HENRY KIM |
| Permit Finaled | 1/8/2021 | JOHN JANSON |
| CofO Issued | 1/8/2021 | JOHN JANSON |
| Permit Finaled | 1/8/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2020 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 3/23/2020 | ROSE MARIE SMITH |
| ZI | Cleared | 3/25/2020 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 4/1/2020 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 4/1/2020 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/21/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 16800 DEVONSHIRE ST SUITE 307 GRANADA HILLS, CA 91344 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/30/2020 | Approved | HENRY KIM |
| Underground Mechanical | 6/30/2020 | Partial Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 7/2/2020 | Not Ready for Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 7/7/2020 | Not Ready for Inspection | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 7/9/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 7/16/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Approved | HENRY KIM |
| Underground Mechanical | 8/13/2020 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/18/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 8/21/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 8/21/2020 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 8/21/2020 | Corrections Issued | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 8/21/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 8/27/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 8/27/2020 | Approved | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 8/27/2020 | Not Ready for Inspection | HENRY KIM |
| Underground Mechanical | 8/27/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 9/10/2020 | Approved | HENRY KIM |
| Insulation | 9/10/2020 | Approved | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 9/10/2020 | Approved | HENRY KIM |
| Drywall Nailing | 9/15/2020 | Approved | HENRY KIM |
| Shower Pan | 10/1/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/12/2020 | Corrections Issued | HENRY KIM |
| Final | 11/12/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 11/12/2020 | Corrections Issued | HENRY KIM |
| HVAC-Final | 11/12/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 11/12/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 11/12/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/20/2020 | Not Ready for Inspection | HENRY KIM |
| Final | 11/20/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 11/20/2020 | Approved | HENRY KIM |
| HVAC-Final | 11/20/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 11/20/2020 | Approved | HENRY KIM |
| Service/Power Release | 11/20/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 12/8/2020 | Approved | HENRY KIM |
| Final | 12/8/2020 | Corrections Issued | HENRY KIM |
| Final | 12/31/2020 | OK to Issue CofO | HENRY KIM |