17165 W RINALDI ST 91344

Certificate Information: 17165 W RINALDI ST 91344

Application / Permit
20014-10000-00661
Plan Check / Job No.
B20LA02832
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 STORY ADU ADDITION TO (E) GARAGE PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JESSE ARELLANO
Corrections Issued 3/25/2020 JESSE ARELLANO
Quality Review Completed 4/2/2020 BILL STUTSMAN
Green Plans Picked Up 6/18/2020 APPLICANT
Applicant returned to address corrections 7/3/2020 JESSE ARELLANO
Applicant returned to address corrections 4/7/2021 JESSE ARELLANO
Plan Check Approved 4/21/2021 JESSE ARELLANO
Building Plans Picked Up 4/22/2021 APPLICANT
Issued 9/1/2021 APPLICANT
CofO in Progress 3/22/2022 DAVID SCANTLIN
No Progress 5/9/2022 MICHAEL SMITH
CofO in Progress 5/10/2022 MICHAEL SMITH
CofO Issued 5/10/2022 MICHAEL SMITH
Permit Finaled 5/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 6/7/2020 RIDWAN HARDY
Green Code Cleared 6/18/2020 DONALD CRICHLOW
Address approval Cleared 8/6/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/6/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ABDULLAH SADOZAI
Low Impact Development Cleared 11/17/2020 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 2/27/2021 JEREMY CARTER
Grading Pre-Inspection Cleared 4/7/2021 JESSE ARELLANO
Roof/Waste drainage to street Cleared 4/15/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Schebler Construction Inc; Lic. No.: 302595-B 6700 JULLIARD AVENUE      MOORPARK, CA 93021
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/7/2021 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 9/21/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 10/7/2021 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 10/18/2021 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 10/22/2021 Not Ready for Inspection RONALD COWAN
HVAC-Rough 10/22/2021 Not Ready for Inspection RONALD COWAN
PLUMBING-Rough 10/22/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 10/25/2021 Approved DAVID SCANTLIN
HVAC-Rough 10/25/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 10/25/2021 Approved DAVID SCANTLIN
Insulation 10/28/2021 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 11/5/2021 Approved DAVID SCANTLIN
Pre-Inspection 12/6/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 1/18/2022 Approved DAVID SCANTLIN
Drywall Nailing 1/18/2022 Approved DAVID SCANTLIN
Final 1/18/2022 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 1/18/2022 Approved DAVID SCANTLIN
Green Building Final 1/18/2022 Approved DAVID SCANTLIN
Green Building Rough 1/18/2022 Approved DAVID SCANTLIN
MERV13>=Final 1/18/2022 Approved DAVID SCANTLIN
MERV13>=Rough 1/18/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 1/18/2022 Approved DAVID SCANTLIN
Final 3/21/2022 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 5/2/2022 Approved DAVID SCANTLIN