465-465 1/2 E 46TH ST 90011
Certificate Information: 465-465 1/2 E 46TH ST 90011
- Application / Permit
- 20014-10000-00620
- Plan Check / Job No.
- B20LA02673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) SFD ( REAR BUILDING ) TO DUPLEX WITH 2ND STORY ADDITION. PROPOSED WORK UNDER UNPERMITTED DWELLING UNIT. NFPA 13D FIRE SPRINKLER THROUGHOUT.
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/17/2020 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 3/22/2020 | YOUNG KIM |
| Applicant returned to address corrections | 6/29/2020 | FARSHAD ALIMOHAMADI |
| Green Plans Picked Up | 8/18/2020 | APPLICANT |
| Building Plans Picked Up | 4/15/2021 | APPLICANT |
| Applicant returned to address corrections | 8/4/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/6/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/13/2021 | FARSHAD ALIMOHAMADI |
| Issued | 8/13/2021 | APPLICANT |
| CofO in Progress | 8/29/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 3/16/2020 | JEREMY CORONEL |
| ZI | Cleared | 6/30/2020 | DANIEL CORONADO |
| Address approval | Cleared | 7/6/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | EMIL KYUPELYAN |
| Tenant Habitability Plan | Cleared | 7/9/2020 | PHILLIP MUNGUIA |
| Green Code | Cleared | 8/14/2020 | FARSHAD ALIMOHAMADI |
| Density Bonus 14.00.A.10 | Cleared | 4/1/2021 | LOUIE MILLER |
| Miscellaneous | Cleared | 6/29/2021 | AIDA KARAPETIAN |
| Unpermitted Dwelling Unit | Cleared | 6/29/2021 | AIDA KARAPETIAN |
| Low Impact Development | Cleared | 7/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/23/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 8/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/20/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 8/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 8/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/20/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/29/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/7/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/27/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 1/28/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/4/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/10/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Off-Hour Fees Due | |
| Insulation | 6/30/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 6/30/2022 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 9/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Final | 9/7/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 9/13/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 9/13/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 9/13/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Rough-Elec/Plmb/HVAC | 9/13/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 9/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 9/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| HVAC-Rough | 9/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Rough-Elec/Plmb/HVAC | 9/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Special/Order Compliance | 9/20/2022 | Not Ready for Inspection | HORACE FULTZ |
| Special/Order Compliance | 9/21/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Rough | 9/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 9/27/2022 | Approved | SHAVONNE ESPINOZA |
| Special/Order Compliance | 9/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | HORACE FULTZ |
| Final | 10/11/2022 | Conditional Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 10/11/2022 | Approved | HORACE FULTZ |
| Green Building Final | 10/11/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 10/11/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 10/11/2022 | Approved | HORACE FULTZ |
| Final | 7/11/2023 | Partial Inspection | CHARLES BOGHOSKHAN |
| Final | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/28/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/28/2023 | Approved | ALEJANDRO DE ARTOLA |