4028 W BRUNSWICK AVE 90039

Certificate Information: 4028 W BRUNSWICK AVE 90039

Application / Permit
20014-10000-00613
Plan Check / Job No.
B20LA02661
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
10' X 18'-7" PATIO ADDITION TO (E) GARAGE & CONVERT IT TO ADU NFPA 13D sprinklers required
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofO Issued on 2/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 JESSE ARELLANO
Corrections Issued 3/25/2020 JESSE ARELLANO
Quality Review Completed 4/2/2020 BILL STUTSMAN
Building Plans Picked Up 4/6/2020 APPLICANT
Applicant returned to address corrections 9/10/2020 JESSE ARELLANO
Green Plans Picked Up 9/17/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 JESSE ARELLANO
Applicant returned to address corrections 11/18/2020 JESSE ARELLANO
Plan Check Approved 12/8/2020 JESSE ARELLANO
Issued 1/6/2021 APPLICANT
CofO in Progress 1/27/2022 ALFREDO BALANDRA
CofO Issued 2/8/2022 DANIEL SANCHEZ
Permit Finaled 2/8/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 4/16/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/16/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 4/16/2020 CECILIO NAVARRO
Sewer availability Cleared 4/16/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 8/18/2020 MATTHEW CRAIG
Green Code Cleared 8/25/2020 KHEDER ALRAZAA

Contact Information

Contractor Sermag Construction; Lic. No.: 1009109-B 7357 ROUND HILL DR      LANCASTER, CA 93536
Engineer Ahmed,, Sarah Zinnurayen; Lic. No.: C82797 5533 PINE AVE      CHINO HILLS, CA 91709

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2021 Corrections Issued TIMOTHY MCCURDY
Footing/Foundation/Slab 4/1/2021 Corrections Issued ROBERT MINASSIANS
Footing/Foundation/Slab 5/20/2021 Approved TIMOTHY MCCURDY
ELECTRICAL-Rough 7/9/2021 Corrections Issued TIMOTHY MCCURDY
PLUMBING-Rough 7/9/2021 Corrections Issued TIMOTHY MCCURDY
Underground Mechanical 8/10/2021 Partial Approval TIMOTHY MCCURDY
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 10/19/2021 Not Ready for Inspection PIERRE VEGA
Green Building Rough 10/19/2021 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 10/19/2021 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 10/29/2021 Approved TIMOTHY MCCURDY
PLUMBING-Rough 10/29/2021 Approved TIMOTHY MCCURDY
Sewer 10/29/2021 Approved TIMOTHY MCCURDY
BUILDING-Rough-Frame 11/18/2021 Corrections Issued TIMOTHY MCCURDY
Green Building Rough 11/18/2021 Not Ready for Inspection TIMOTHY MCCURDY
Special/Order Compliance 11/18/2021 Partial Inspection PIERRE VEGA
Insulation 12/2/2021 Approved TIMOTHY MCCURDY
Special/Order Compliance 12/2/2021 Partial Inspection PIERRE VEGA
Drywall Nailing 12/9/2021 Approved TIMOTHY MCCURDY
Green Building Rough 12/9/2021 Approved TIMOTHY MCCURDY
Interior/Exterior Lathing 12/9/2021 Approved TIMOTHY MCCURDY
BUILDING-Rough-Frame 1/4/2022 Approved TIMOTHY MCCURDY
ELECTRICAL-Final 1/4/2022 Approved TIMOTHY MCCURDY
Final 1/4/2022 Corrections Issued TIMOTHY MCCURDY
Green Building Final 1/4/2022 Approved TIMOTHY MCCURDY
HVAC-Final 1/4/2022 Approved TIMOTHY MCCURDY
PLUMBING-Final 1/4/2022 Approved TIMOTHY MCCURDY
SGSOV-Seismic Gas S/O Valve 1/4/2022 SGSOV Not Ready TIMOTHY MCCURDY
Smoke Detectors 1/4/2022 Approved TIMOTHY MCCURDY
Final 1/26/2022 OK to Issue CofO ALFREDO BALANDRA
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved ALFREDO BALANDRA