4028 W BRUNSWICK AVE 90039
Certificate Information: 4028 W BRUNSWICK AVE 90039
- Application / Permit
- 20014-10000-00613
- Plan Check / Job No.
- B20LA02661
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 10' X 18'-7" PATIO ADDITION TO (E) GARAGE & CONVERT IT TO ADU NFPA 13D sprinklers required
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | JESSE ARELLANO |
| Corrections Issued | 3/25/2020 | JESSE ARELLANO |
| Quality Review Completed | 4/2/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 4/6/2020 | APPLICANT |
| Applicant returned to address corrections | 9/10/2020 | JESSE ARELLANO |
| Green Plans Picked Up | 9/17/2020 | APPLICANT |
| Applicant returned to address corrections | 10/5/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 11/18/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/8/2020 | JESSE ARELLANO |
| Issued | 1/6/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | ALFREDO BALANDRA |
| CofO Issued | 2/8/2022 | DANIEL SANCHEZ |
| Permit Finaled | 2/8/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 4/16/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/16/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 8/18/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 8/25/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Sermag Construction; Lic. No.: 1009109-B | 7357 ROUND HILL DR LANCASTER, CA 93536 |
| Engineer | Ahmed,, Sarah Zinnurayen; Lic. No.: C82797 | 5533 PINE AVE CHINO HILLS, CA 91709 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Footing/Foundation/Slab | 4/1/2021 | Corrections Issued | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 5/20/2021 | Approved | TIMOTHY MCCURDY |
| ELECTRICAL-Rough | 7/9/2021 | Corrections Issued | TIMOTHY MCCURDY |
| PLUMBING-Rough | 7/9/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Underground Mechanical | 8/10/2021 | Partial Approval | TIMOTHY MCCURDY |
| BUILDING-Rough-Frame | 10/19/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 10/19/2021 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 10/19/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 10/29/2021 | Approved | TIMOTHY MCCURDY |
| PLUMBING-Rough | 10/29/2021 | Approved | TIMOTHY MCCURDY |
| Sewer | 10/29/2021 | Approved | TIMOTHY MCCURDY |
| BUILDING-Rough-Frame | 11/18/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | TIMOTHY MCCURDY |
| Special/Order Compliance | 11/18/2021 | Partial Inspection | PIERRE VEGA |
| Insulation | 12/2/2021 | Approved | TIMOTHY MCCURDY |
| Special/Order Compliance | 12/2/2021 | Partial Inspection | PIERRE VEGA |
| Drywall Nailing | 12/9/2021 | Approved | TIMOTHY MCCURDY |
| Green Building Rough | 12/9/2021 | Approved | TIMOTHY MCCURDY |
| Interior/Exterior Lathing | 12/9/2021 | Approved | TIMOTHY MCCURDY |
| BUILDING-Rough-Frame | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| ELECTRICAL-Final | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| Final | 1/4/2022 | Corrections Issued | TIMOTHY MCCURDY |
| Green Building Final | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| HVAC-Final | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| PLUMBING-Final | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Not Ready | TIMOTHY MCCURDY |
| Smoke Detectors | 1/4/2022 | Approved | TIMOTHY MCCURDY |
| Final | 1/26/2022 | OK to Issue CofO | ALFREDO BALANDRA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | ALFREDO BALANDRA |