2319 N ECHO PARK AVE 90026
Certificate Information: 2319 N ECHO PARK AVE 90026
- Application / Permit
- 20014-10000-00571
- Plan Check / Job No.
- B20LA02543
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EXISTING SFD. (1 OF 3)
- Permit Issued
- Issued on 3/6/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/13/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/18/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| Green Plans Picked Up | 9/24/2020 | APPLICANT |
| Applicant returned to address corrections | 10/22/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/27/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 11/24/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 12/28/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/5/2021 | CRYSTEL MAALOUF |
| Issued | 3/6/2021 | APPLICANT |
| CofO in Progress | 11/3/2022 | THOMAS LOGRASSO |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| CofO Issued | 11/19/2022 | DEROLD HAUFF |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 9/21/2020 | VIVIAN LAO |
| Roof/Waste drainage to street | Cleared | 11/9/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | WALLIE JONG |
| Sewer availability | Cleared | 11/18/2020 | WALLIE JONG |
| GPI Written Notices | Cleared | 12/8/2020 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 12/8/2020 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Alexander Building Co; Lic. No.: 980164-B | 1809 PARK DRIVE LOS ANGELES, CA 90026 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 12831 PANAMA STREET LOS ANGELES, CA 90066 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Piling/Pier/Caisson | 5/19/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 5/24/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 6/2/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 6/2/2021 | Partial Approval | RUBEN SALAS |
| Deputy Reinf. Concrete | 6/3/2021 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 7/16/2021 | Approved | RUBEN SALAS |
| Deputy Reinf. Concrete | 7/20/2021 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/21/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/21/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 1/27/2022 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 2/4/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/9/2022 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/9/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 2/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 3/3/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 6/22/2022 | Approved | JOSE AVILA |
| Shower Pan | 6/22/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/22/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/22/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 9/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 9/22/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/22/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 9/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | THOMAS LOGRASSO |
| Final | 10/27/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 10/27/2022 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 10/27/2022 | Approved | THOMAS LOGRASSO |
| Final | 11/3/2022 | OK to Issue CofO | THOMAS LOGRASSO |