2244 N RIDGEMONT DR 90046
Certificate Information: 2244 N RIDGEMONT DR 90046
- Application / Permit
- 20014-10000-00526
- Plan Check / Job No.
- B20LA02404
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 431 SQ FT ADDITION AND MAJOR INTERIOR REMODEL TO EXISTING SFD 1 OF 2
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2020 | STARR CHEN |
| Green Plans Picked Up | 2/21/2020 | APPLICANT |
| Corrections Issued | 2/25/2020 | STARR CHEN |
| Quality Review Completed | 2/26/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2020 | STARR CHEN |
| Plan Check Approved | 8/18/2020 | STARR CHEN |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 12/20/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 12/20/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 6/15/2022 | DEROLD HAUFF |
| CofO Issued | 6/15/2022 | DEROLD HAUFF |
| Permit Finaled | 6/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/12/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/12/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 3/12/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | WALLIE JONG |
| Sewer availability | Cleared | 3/12/2020 | WALLIE JONG |
| Distance to fire station | Cleared | 3/13/2020 | JOHN CONNEALLY |
| Green Code | Cleared | 3/18/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 6/28/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 8/18/2020 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 8/18/2020 | STARR CHEN |
Contact Information
| Architect | Cataldo,, John G; Lic. No.: C10457 | 835 MISSION STREET SOUTH PASADENA, CA 91030 |
| Contractor | Encore Development Co; Lic. No.: 876396-B | 20620 S LEAPWOOD AVENUE STE G CARSON, CA 90746 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/27/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/18/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/28/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/29/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/29/2020 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 9/29/2020 | Corrections Issued | RAUL BARAJAS |
| Pre-Inspection | 11/9/2020 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/18/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 11/18/2020 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/17/2020 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/17/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 12/17/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/17/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/17/2020 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/21/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/21/2020 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 12/21/2020 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/24/2020 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/24/2020 | Approved | RAUL BARAJAS |
| Green Building Rough | 12/24/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 12/24/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 12/24/2020 | Approved | RAUL BARAJAS |
| Insulation | 1/8/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/8/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/14/2021 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 2/4/2021 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/16/2021 | Approved | RAUL BARAJAS |
| Final | 4/16/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/16/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 4/16/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 4/16/2021 | Approved | RAUL BARAJAS |
| Final | 12/17/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Approved | ARTHUR SARGSYAN |