11942 W CHARNOCK ROAD 90066
Certificate Information: 11942 W CHARNOCK ROAD 90066
- Application / Permit
- 20014-10000-00519
- Plan Check / Job No.
- B20LA02368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING AND ALTERATION. INSTALL FIRE SPRINLERS THROUGHOUT NFPA 13D (1 OF 2)
- Permit Issued
- Issued on 12/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | ALBERT SERVIN |
| Corrections Issued | 3/2/2020 | ALBERT SERVIN |
| Quality Review Completed | 3/2/2020 | KEN GILL |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Green Plans Picked Up | 6/15/2020 | APPLICANT |
| Plan Check Approved | 7/22/2020 | ALBERT SERVIN |
| Issued | 12/18/2020 | APPLICANT |
| CofO in Progress | 2/2/2023 | JOHNNY MIRANDA |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
| CofO Issued | 2/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/8/2020 | DINAH GARIN |
| Green Code | Cleared | 6/12/2020 | ALBERT SERVIN |
| Low Impact Development | Cleared | 6/18/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 6/26/2020 | DINAH GARIN |
| Miscellaneous | Cleared | 7/1/2020 | RUBEN VASQUEZ |
| GPI Written Notices | Cleared | 7/22/2020 | ALBERT SERVIN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Waconah Construction; Lic. No.: 908219-B | 2431 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Corrections Issued | RICHARD ROBLES |
| Excavation/Setback/Form/Re-Bar | 2/19/2021 | Corrections Issued | RICHARD ROBLES |
| Excavation/Setback/Form/Re-Bar | 2/23/2021 | Approved | RICHARD ROBLES |
| Footing/Foundation/Slab | 3/17/2021 | Partial Approval | EVAN COOPER |
| Reinforced Concrete Frame | 3/22/2021 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 3/26/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/5/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/5/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Reinforced Masonry Frame | 4/28/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/3/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/9/2021 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 8/16/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/17/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | EVAN COOPER |
| Wood Frame | 9/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/16/2021 | Approved | EVAN COOPER |
| Green Building Rough | 9/16/2021 | Approved | EVAN COOPER |
| Insulation | 10/4/2021 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/15/2021 | Approved | EVAN COOPER |
| Shower Pan | 10/15/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 10/22/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/5/2021 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 11/5/2021 | Approved | KENNETH NAGLE |
| Gas Test | 11/10/2021 | Approved | JOHNNY MIRANDA |
| Sewer | 11/10/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/24/2021 | Approved | JOHNNY MIRANDA |
| Wood Frame | 11/24/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/13/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 7/13/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/13/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/23/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/26/2022 | Conditional Approval | JOHN KIDWELL |
| Pre-Inspection | 10/4/2022 | Partial Approval | JOHNNY MIRANDA |
| Final | 10/25/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 10/25/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 10/25/2022 | Approved | ANDREW NAVE |
| Service/Power Release | 10/31/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/25/2023 | OK to Issue CofO | JOHNNY MIRANDA |
| Green Building Final | 1/25/2023 | Approved | JOHNNY MIRANDA |