11942 W CHARNOCK ROAD 90066

Certificate Information: 11942 W CHARNOCK ROAD 90066

Application / Permit
20014-10000-00519
Plan Check / Job No.
B20LA02368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING AND ALTERATION. INSTALL FIRE SPRINLERS THROUGHOUT NFPA 13D (1 OF 2)
Permit Issued
Issued on 12/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 ALBERT SERVIN
Corrections Issued 3/2/2020 ALBERT SERVIN
Quality Review Completed 3/2/2020 KEN GILL
Building Plans Picked Up 3/12/2020 APPLICANT
Green Plans Picked Up 6/15/2020 APPLICANT
Plan Check Approved 7/22/2020 ALBERT SERVIN
Issued 12/18/2020 APPLICANT
CofO in Progress 2/2/2023 JOHNNY MIRANDA
Permit Finaled 2/6/2023 DANIEL ORRANTE
CofO Issued 2/6/2023 DANIEL ORRANTE
Permit Finaled 2/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/8/2020 DINAH GARIN
Green Code Cleared 6/12/2020 ALBERT SERVIN
Low Impact Development Cleared 6/18/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 6/26/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 6/26/2020 DINAH GARIN
Miscellaneous Cleared 7/1/2020 RUBEN VASQUEZ
GPI Written Notices Cleared 7/22/2020 ALBERT SERVIN

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Waconah Construction; Lic. No.: 908219-B 2431 1/2 ABBOT KINNEY BLVD      VENICE, CA 90291
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/12/2021 Corrections Issued RICHARD ROBLES
Excavation/Setback/Form/Re-Bar 2/19/2021 Corrections Issued RICHARD ROBLES
Excavation/Setback/Form/Re-Bar 2/23/2021 Approved RICHARD ROBLES
Footing/Foundation/Slab 3/17/2021 Partial Approval EVAN COOPER
Reinforced Concrete Frame 3/22/2021 Corrections Issued EVAN COOPER
Underground Mechanical 3/26/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 4/5/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/5/2021 Partial Approval OGANES TARAKHCHYAN
Reinforced Masonry Frame 4/28/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 8/3/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/9/2021 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 8/16/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/17/2021 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/10/2021 Partial Approval EVAN COOPER
Wood Frame 9/14/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/16/2021 Approved EVAN COOPER
Green Building Rough 9/16/2021 Approved EVAN COOPER
Insulation 10/4/2021 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/15/2021 Approved EVAN COOPER
Shower Pan 10/15/2021 Approved EVAN COOPER
Drywall Nailing 10/22/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/5/2021 Approved KENNETH NAGLE
PLUMBING-Rough 11/5/2021 Approved KENNETH NAGLE
Gas Test 11/10/2021 Approved JOHNNY MIRANDA
Sewer 11/10/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/24/2021 Approved JOHNNY MIRANDA
Wood Frame 11/24/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 7/13/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/13/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/23/2022 Approved JOHNNY MIRANDA
HVAC-Final 9/26/2022 Conditional Approval JOHN KIDWELL
Pre-Inspection 10/4/2022 Partial Approval JOHNNY MIRANDA
Final 10/25/2022 Corrections Issued ANDREW NAVE
Green Building Final 10/25/2022 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 10/25/2022 Approved ANDREW NAVE
Service/Power Release 10/31/2022 Approved JOHNNY MIRANDA
Final 1/25/2023 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 1/25/2023 Approved JOHNNY MIRANDA