15425 W LEMAY ST 91406

Certificate Information: 15425 W LEMAY ST 91406

Application / Permit
20014-10000-00504
Plan Check / Job No.
B20LA02313
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO THE REAR OF (E) SFD TO ADD 1-BEDRM, 1-BATH. REMODEL KITCHEN-1 STORY. ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 2/13/2020 SHANGQIN XIE
Issued 2/25/2020 LADBS
CofO in Progress 6/21/2021 JACK KARGODORIAN
CofO Issued 9/25/2021 MICHAEL SMITH
Permit Finaled 9/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2020 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/13/2020 JEANETTE VONG
Sewer availability Cleared 2/13/2020 JEANETTE VONG
ZI Cleared 2/13/2020 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/18/2020 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 12/23/2020 Approved DAVID MATSON
Special/Order Compliance 12/23/2020 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 2/11/2021 No Access for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 2/11/2021 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 2/16/2021 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/16/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/24/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/24/2021 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 3/4/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/10/2021 Corrections Issued MICHAEL TEMPLE
Drywall Nailing 3/10/2021 Corrections Issued MICHAEL TEMPLE
Green Building Rough 3/10/2021 Not Ready for Inspection MICHAEL TEMPLE
HVAC-Rough 3/10/2021 Corrections Issued MICHAEL TEMPLE
Drywall Nailing 3/23/2021 Partial Inspection MATTHEW NELSON
Interior/Exterior Lathing 3/23/2021 Approved MATTHEW NELSON
Shower Pan 3/23/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/8/2021 Approved MARK JOHNSON
Drywall Nailing 6/8/2021 Approved MARK JOHNSON
Final 6/8/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 6/8/2021 Approved MARK JOHNSON
Green Building Final 6/8/2021 Approved MARK JOHNSON
Green Building Rough 6/8/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 6/8/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 6/8/2021 Approved MARK JOHNSON
Final 6/15/2021 Corrections Issued MARK JOHNSON
Final 6/21/2021 OK to Issue CofO JACK KARGODORIAN