15425 W LEMAY ST 91406
Certificate Information: 15425 W LEMAY ST 91406
- Application / Permit
- 20014-10000-00504
- Plan Check / Job No.
- B20LA02313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE REAR OF (E) SFD TO ADD 1-BEDRM, 1-BATH. REMODEL KITCHEN-1 STORY. ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/13/2020 | SHANGQIN XIE |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 6/21/2021 | JACK KARGODORIAN |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/13/2020 | JEANETTE VONG |
| ZI | Cleared | 2/13/2020 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/18/2020 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 12/23/2020 | Approved | DAVID MATSON |
| Special/Order Compliance | 12/23/2020 | Approved | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 2/11/2021 | No Access for Inspection | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 2/11/2021 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/16/2021 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 2/16/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/24/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/24/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 3/4/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/10/2021 | Corrections Issued | MICHAEL TEMPLE |
| Drywall Nailing | 3/10/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 3/10/2021 | Corrections Issued | MICHAEL TEMPLE |
| Drywall Nailing | 3/23/2021 | Partial Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/23/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 3/23/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/8/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 6/8/2021 | Approved | MARK JOHNSON |
| Final | 6/8/2021 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 6/8/2021 | Approved | MARK JOHNSON |
| Green Building Final | 6/8/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 6/8/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 6/8/2021 | Approved | MARK JOHNSON |
| Final | 6/15/2021 | Corrections Issued | MARK JOHNSON |
| Final | 6/21/2021 | OK to Issue CofO | JACK KARGODORIAN |