5129 N EAGLE ROCK BLVD 90041
Certificate Information: 5129 N EAGLE ROCK BLVD 90041
- Application / Permit
- 20014-10000-00487
- Plan Check / Job No.
- B20LA02231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT AND ADD 70 S.F. PATIO COVER.
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofO Issued on 7/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | RAHEL BEYENE |
| Corrections Issued | 2/5/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 5/18/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/3/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 6/22/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 7/8/2020 | FERNANDO FLORES |
| Issued | 7/15/2020 | APPLICANT |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | CRAIG VAUGHAN |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
| CofO Issued | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 2/5/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/5/2020 | EMIL KYUPELYAN |
| ZA Case | Cleared | 3/31/2020 | RICHARD REASER |
| ZA Case | Cleared | 3/31/2020 | RICHARD REASER |
| Construction near power lines | Cleared | 4/25/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/6/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2020 | Partial Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/27/2020 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 8/27/2020 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 9/10/2020 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/11/2020 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 9/11/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/14/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 10/14/2020 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 10/23/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 11/2/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/2/2020 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 11/2/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/17/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 11/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 11/17/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 11/17/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/17/2020 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/8/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/8/2020 | Approved | CRAIG VAUGHAN |
| Shower Pan | 12/8/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 12/16/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/18/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/18/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 3/18/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 3/18/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 3/18/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/18/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/6/2021 | Corrections Issued | CRAIG VAUGHAN |
| Final | 4/6/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 4/6/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 4/6/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 4/6/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/7/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 6/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 6/7/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| Final | 6/16/2021 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 6/16/2021 | Partial Inspection | COREY HUPP |
| ELECTRICAL-Final | 6/30/2021 | Approved | CRAIG VAUGHAN |
| Final | 6/30/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 6/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 6/30/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/30/2021 | Approved | CRAIG VAUGHAN |