2015 W 42ND PL 90062
Certificate Information: 2015 W 42ND PL 90062
- Application / Permit
- 20014-10000-00477
- Plan Check / Job No.
- B20LA02171
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION, INTERIOR REMODEL, NEW DECK TO EXISTING SFD
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 6/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2020 | MONICA RAMIREZ |
| Corrections Issued | 2/10/2020 | MONICA RAMIREZ |
| Plan Check Approved | 2/18/2020 | CRISTINA SALAZAR |
| Issued | 4/29/2021 | APPLICANT |
| CofO in Progress | 6/18/2025 | SABAS ALONSO |
| Permit Finaled | 6/24/2025 | DEROLD HAUFF |
| CofO Issued | 6/24/2025 | DEROLD HAUFF |
| Permit Finaled | 6/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 2/13/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/13/2020 | THOMAS LANG |
Contact Information
| Contractor | Jungong Construction Inc; Lic. No.: 1029363-B | 925 S ATLANTIC BLVD #216 MONTEREY PARK, CA 91754 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/11/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/20/2021 | Approved | ROBERT MCDOWELL |
| Deputy Drilled-In Anchors | 5/21/2021 | Approved | HORACE FULTZ |
| Wood Frame | 7/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 12/9/2022 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 12/9/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 1/20/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 1/20/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/26/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 1/26/2023 | No Access for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/12/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 1/12/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 1/12/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 1/30/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 1/30/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 1/30/2024 | Approved | SABAS ALONSO |
| Wood Frame | 1/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 5/22/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Approved | SABAS ALONSO |
| Wood Frame | 8/28/2024 | No Access for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 8/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 8/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 9/9/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 9/17/2024 | Partial Approval | SABAS ALONSO |
| Wood Frame | 9/17/2024 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 10/10/2024 | Approved | SABAS ALONSO |
| Insulation | 10/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 10/22/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/29/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/29/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 11/4/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 11/12/2024 | Approved | SABAS ALONSO |
| Shower Pan | 11/12/2024 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 11/15/2024 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 11/20/2024 | Approved | SABAS ALONSO |
| Final | 3/5/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/5/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 3/5/2025 | Approved | SABAS ALONSO |
| Final | 4/18/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/18/2025 | Approved | SABAS ALONSO |
| Final | 5/7/2025 | Corrections Issued | SABAS ALONSO |
| Final | 6/16/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 6/16/2025 | Approved | SABAS ALONSO |