2015 W 42ND PL 90062

Certificate Information: 2015 W 42ND PL 90062

Application / Permit
20014-10000-00477
Plan Check / Job No.
B20LA02171
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION, INTERIOR REMODEL, NEW DECK TO EXISTING SFD
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 6/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/10/2020 MONICA RAMIREZ
Corrections Issued 2/10/2020 MONICA RAMIREZ
Plan Check Approved 2/18/2020 CRISTINA SALAZAR
Issued 4/29/2021 APPLICANT
CofO in Progress 6/18/2025 SABAS ALONSO
Permit Finaled 6/24/2025 DEROLD HAUFF
CofO Issued 6/24/2025 DEROLD HAUFF
Permit Finaled 6/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/13/2020 THOMAS LANG
Low Impact Development Cleared 2/13/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/13/2020 THOMAS LANG
Sewer availability Cleared 2/13/2020 THOMAS LANG

Contact Information

Contractor Jungong Construction Inc; Lic. No.: 1029363-B 925 S ATLANTIC BLVD #216      MONTEREY PARK, CA 91754
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 5/20/2021 Approved ROBERT MCDOWELL
Deputy Drilled-In Anchors 5/21/2021 Approved HORACE FULTZ
Wood Frame 7/28/2021 Not Ready for Inspection SABAS ALONSO
Rough-Elec/Plmb/HVAC 12/9/2022 Not Ready for Inspection SABAS ALONSO
Wood Frame 12/9/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 1/20/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 1/20/2023 Approved SABAS ALONSO
Drywall Nailing 1/26/2023 No Access for Inspection ENRIQUE MIRELES
Insulation 1/26/2023 No Access for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 1/12/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Partial Approval SABAS ALONSO
HVAC-Rough 1/12/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 1/12/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 1/30/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 1/30/2024 Approved SABAS ALONSO
PLUMBING-Rough 1/30/2024 Approved SABAS ALONSO
Wood Frame 1/30/2024 Not Ready for Inspection SABAS ALONSO
Deputy Wood Construction 5/22/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Approved SABAS ALONSO
Wood Frame 8/28/2024 No Access for Inspection SABAS ALONSO
Interior/Exterior Lathing 8/29/2024 Not Ready for Inspection SABAS ALONSO
Wood Frame 8/29/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 9/9/2024 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 9/17/2024 Partial Approval SABAS ALONSO
Wood Frame 9/17/2024 No Access for Inspection SABAS ALONSO
BUILDING-Rough-Frame 10/10/2024 Approved SABAS ALONSO
Green Building Rough 10/10/2024 Approved SABAS ALONSO
Insulation 10/17/2024 Not Ready for Inspection SABAS ALONSO
Insulation 10/22/2024 Approved SABAS ALONSO
Drywall Nailing 10/29/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 10/29/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/4/2024 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 11/12/2024 Approved SABAS ALONSO
Shower Pan 11/12/2024 Corrections Issued SABAS ALONSO
Shower Pan 11/15/2024 Corrections Issued SABAS ALONSO
Shower Pan 11/20/2024 Approved SABAS ALONSO
Final 3/5/2025 Corrections Issued SABAS ALONSO
Green Building Final 3/5/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 3/5/2025 Approved SABAS ALONSO
Final 4/18/2025 Corrections Issued SABAS ALONSO
Green Building Final 4/18/2025 Approved SABAS ALONSO
Final 5/7/2025 Corrections Issued SABAS ALONSO
Final 6/16/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 6/16/2025 Approved SABAS ALONSO