231 W 82ND ST 90003

Certificate Information: 231 W 82ND ST 90003

Application / Permit
20014-10000-00463
Plan Check / Job No.
B20LA02098
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH (N) ADDITION TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 3/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 KEVIN MORALES
Corrections Issued 2/10/2020 KEVIN MORALES
Plan Check Approved 2/19/2020 KEVIN MORALES
Issued 3/3/2020 LADBS
CofO in Progress 12/13/2021 JOAQUIN GREENOUGH
CofO in Progress 12/13/2021 JOAQUIN GREENOUGH
CofO in Progress 1/20/2022 ALIZAH MAYAGOITIA
Permit Finaled 2/26/2022 DEROLD HAUFF
CofO Issued 2/26/2022 DEROLD HAUFF
Permit Finaled 2/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/18/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/18/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 2/18/2020 JUAN ASHTON
Sewer availability Cleared 2/18/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/13/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/16/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/28/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 8/24/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 8/27/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 8/27/2020 Not Ready for Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 9/1/2020 Approved COREY HUPP
Wood Frame 9/1/2020 Approved COREY HUPP
Insulation 9/4/2020 Approved DAVID FEILER
Interior/Exterior Lathing 9/4/2020 Partial Approval DAVID FEILER
Drywall Nailing 9/10/2020 No Access for Inspection DAVID FEILER
Green Building Rough 9/10/2020 No Access for Inspection DAVID FEILER
Drywall Nailing 9/14/2020 Approved DONALD CRICHLOW
Green Building Rough 9/14/2020 Approved DONALD CRICHLOW
Special/Order Compliance 9/14/2020 Approved DONALD CRICHLOW
Final 1/26/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/26/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/26/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 1/26/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 1/26/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/27/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Not Ready EUGENE CASSIDY
BUILDING-Rough-Frame 7/12/2021 Not Ready for Inspection FREDDIE RIVERA
Final 7/12/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 7/12/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 7/12/2021 Not Ready for Inspection FREDDIE RIVERA
Final 7/29/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 7/29/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/29/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 7/29/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 8/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/3/2021 Approved HORACE FULTZ
Final 11/3/2021 Corrections Issued HORACE FULTZ
Green Building Final 11/3/2021 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready HORACE FULTZ
Smoke Detectors 11/3/2021 Approved HORACE FULTZ
Final 12/10/2021 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 12/10/2021 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved ALIZAH MAYAGOITIA
Final 12/20/2021 Corrections Issued ALIZAH MAYAGOITIA
Final 1/20/2022 OK to Issue CofO ALIZAH MAYAGOITIA