231 W 82ND ST 90003
Certificate Information: 231 W 82ND ST 90003
- Application / Permit
- 20014-10000-00463
- Plan Check / Job No.
- B20LA02098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH (N) ADDITION TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2020 | KEVIN MORALES |
| Corrections Issued | 2/10/2020 | KEVIN MORALES |
| Plan Check Approved | 2/19/2020 | KEVIN MORALES |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 12/13/2021 | JOAQUIN GREENOUGH |
| CofO in Progress | 12/13/2021 | JOAQUIN GREENOUGH |
| CofO in Progress | 1/20/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
| CofO Issued | 2/26/2022 | DEROLD HAUFF |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 2/18/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/7/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/13/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/16/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/28/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/24/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 8/24/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/24/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/27/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 8/27/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/1/2020 | Approved | COREY HUPP |
| Wood Frame | 9/1/2020 | Approved | COREY HUPP |
| Insulation | 9/4/2020 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 9/4/2020 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 9/10/2020 | No Access for Inspection | DAVID FEILER |
| Green Building Rough | 9/10/2020 | No Access for Inspection | DAVID FEILER |
| Drywall Nailing | 9/14/2020 | Approved | DONALD CRICHLOW |
| Green Building Rough | 9/14/2020 | Approved | DONALD CRICHLOW |
| Special/Order Compliance | 9/14/2020 | Approved | DONALD CRICHLOW |
| Final | 1/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 1/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/26/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/27/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 7/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 7/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 7/12/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 7/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 7/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/29/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | HORACE FULTZ |
| Final | 11/3/2021 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 11/3/2021 | Corrections Issued | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 11/3/2021 | Approved | HORACE FULTZ |
| Final | 12/10/2021 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 12/10/2021 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 12/20/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 1/20/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |