15144 W CALIFA ST 91411

Certificate Information: 15144 W CALIFA ST 91411

Application / Permit
20014-10000-00439
Plan Check / Job No.
B20LA02010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ADDITION & CONVERT GARAGE INTO ACCESSORY DWELLING UNIT ALL WORK PER WFPP
Permit Issued
Issued on 2/19/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/3/2020 MONICA RAMIREZ
Corrections Issued 2/3/2020 MONICA RAMIREZ
Plan Check Approved 2/14/2020 FERNANDO FLORES
Issued 2/19/2020 LADBS
CofO in Progress 8/25/2020 WILLIAM KUEHN
CofO in Progress 10/27/2020 MICHAEL TEMPLE
CofO in Progress 5/22/2021 MICHAEL TEMPLE
CofO Issued 7/3/2021 MICHAEL SMITH
Permit Finaled 7/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/3/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/3/2020 ERIK BEASLEY
Sewer availability Cleared 2/6/2020 THOMAS LANG
Low Impact Development Cleared 2/13/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/14/2020 JEANETTE VONG

Contact Information

Contractor Precision Construction Experts Inc; Lic. No.: 1026997-B 16656 CALLE ARBOLADA      PACIFIC PALISADES, CA 90272

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/25/2020 Not Ready for Inspection MISAEL ESPARZA
METHANE-Barrier 2/25/2020 Approved MISAEL ESPARZA
METHANE-Subgrade 2/25/2020 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/2/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/2/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/6/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/6/2020 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/6/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/6/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/6/2020 Not Ready for Inspection MISAEL ESPARZA
METHANE-Rough 3/6/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 3/6/2020 Corrections Issued MISAEL ESPARZA
Wood Frame 3/6/2020 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/9/2020 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/12/2020 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 3/12/2020 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/18/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 3/18/2020 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 3/25/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 3/25/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/25/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/25/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/27/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 3/27/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/27/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/31/2020 Approved MISAEL ESPARZA
HVAC-Rough 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/31/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/31/2020 SGSOV Not Ready MISAEL ESPARZA
Wood Frame 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/1/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/1/2020 Approved MISAEL ESPARZA
Green Building Rough 4/1/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 4/1/2020 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/1/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/1/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/8/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 4/8/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/8/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 4/8/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/16/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/16/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval MISAEL ESPARZA
Insulation 4/17/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 4/23/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/23/2020 Partial Approval MISAEL ESPARZA
Shower Pan 4/23/2020 Approved MISAEL ESPARZA
Drywall Nailing 4/27/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/4/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Final 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/4/2020 Corrections Issued MISAEL ESPARZA
Gas Test 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 6/4/2020 Approved MISAEL ESPARZA
HVAC-Final 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Final 7/10/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 7/10/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 7/10/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/10/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/5/2020 Not Ready for Inspection WILLIAM KUEHN
Final 8/5/2020 No Access for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection WILLIAM KUEHN
Gas Test 8/5/2020 No Access for Inspection WILLIAM KUEHN
Green Building Final 8/5/2020 No Access for Inspection WILLIAM KUEHN
HVAC-Final 8/5/2020 No Access for Inspection WILLIAM KUEHN
PLUMBING-Final 8/5/2020 No Access for Inspection WILLIAM KUEHN
Service/Power Release 8/5/2020 No Access for Inspection WILLIAM KUEHN
Final 8/24/2020 Conditional Approval WILLIAM KUEHN
Footing/Foundation/Slab 8/24/2020 Approved WILLIAM KUEHN
Green Building Final 8/24/2020 Approved WILLIAM KUEHN
Special/Order Compliance 10/27/2020 Corrections Issued MICHAEL TEMPLE
Final 1/26/2021 Not Ready for Inspection ARTHUR SARGSYAN