3810 S BURNSIDE AVE 90008

Certificate Information: 3810 S BURNSIDE AVE 90008

Application / Permit
20014-10000-00438
Plan Check / Job No.
B20LA02005
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
LAUNDRY ROOM ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/3/2020 SHANGQIN XIE
Corrections Issued 2/3/2020 SHANGQIN XIE
Applicant returned to address corrections 2/5/2020 SHANGQIN XIE
Plan Check Approved 3/10/2020 MONICA RAMIREZ
Issued 3/10/2020 LADBS
CofO in Progress 9/8/2020 JOSEPH MCGARRY
Permit Finaled 9/24/2020 DEROLD HAUFF
Permit Finaled 9/24/2020 DEROLD HAUFF
CofO Issued 9/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/3/2020 ELAINE LEI
Grading Pre-Inspection Cleared 2/3/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 2/3/2020 THOMAS LANG
Construction within easement Cleared 2/5/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 4/28/2020 Approved COREY HUPP
BUILDING-Rough-Frame 5/21/2020 Partial Approval COREY HUPP
PLUMBING-Rough 5/21/2020 Partial Approval COREY HUPP
BUILDING-Rough-Frame 6/11/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/11/2020 Corrections Issued FREDDIE RIVERA
Green Building Rough 6/11/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 6/19/2020 Approved SABAS ALONSO
ELECTRICAL-Rough 6/19/2020 Approved SABAS ALONSO
Green Building Rough 6/19/2020 Approved SABAS ALONSO
PLUMBING-Rough 6/19/2020 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/1/2020 Approved SABAS ALONSO
Insulation 7/15/2020 Approved SABAS ALONSO
Drywall Nailing 7/20/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/20/2020 Approved SABAS ALONSO
ELECTRICAL-Final 9/8/2020 Approved JOSEPH MCGARRY
Final 9/8/2020 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 9/8/2020 Approved JOSEPH MCGARRY
HVAC-Final 9/8/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 9/8/2020 Approved JOSEPH MCGARRY
Smoke Detectors 9/8/2020 Approved JOSEPH MCGARRY