2047 W 84TH PL 90047
Certificate Information: 2047 W 84TH PL 90047
- Application / Permit
- 20014-10000-00423
- Plan Check / Job No.
- B20LA01943
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to ADU per LAMC 12.22 A.33(c) and (d) with one-story addition.
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2020 | ADAM HEGAZI |
| Corrections Issued | 1/31/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/22/2020 | TSE MING HUANG |
| Plan Check Approved | 10/30/2020 | TSE MING HUANG |
| Issued | 6/21/2021 | APPLICANT |
| Building Plans Picked Up | 6/22/2021 | APPLICANT |
| CofO in Progress | 4/18/2023 | ENRIQUE MIRELES |
| CofO in Progress | 4/18/2023 | ENRIQUE MIRELES |
| CofO Issued | 8/10/2023 | DEROLD HAUFF |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/23/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/23/2020 | RIDWAN HARDY |
| Address approval | Cleared | 8/31/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | THOMAS LANG |
| Sewer availability | Cleared | 9/3/2020 | THOMAS LANG |
Contact Information
| Contractor | Whittington Matthew; Lic. No.: 683085-B | 5722 MUSCATEL AVE SAN GABRIEL, CA 91775 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2021 | Not Ready for Inspection | HORACE FULTZ |
| Footing/Foundation/Slab | 2/8/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Inspection | 2/14/2022 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 3/10/2022 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 3/15/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/25/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/6/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/9/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 11/16/2022 | Corrections Issued | RYAN SALAZAR |
| Insulation | 11/22/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/7/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/7/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/11/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/11/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/11/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/19/2023 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 1/19/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/22/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/1/2023 | OK to Issue CofO | ENRIQUE MIRELES |