2047 W 84TH PL 90047

Certificate Information: 2047 W 84TH PL 90047

Application / Permit
20014-10000-00423
Plan Check / Job No.
B20LA01943
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to ADU per LAMC 12.22 A.33(c) and (d) with one-story addition.
Permit Issued
Issued on 6/21/2021
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/31/2020 ADAM HEGAZI
Corrections Issued 1/31/2020 ADAM HEGAZI
Applicant returned to address corrections 10/22/2020 TSE MING HUANG
Plan Check Approved 10/30/2020 TSE MING HUANG
Issued 6/21/2021 APPLICANT
Building Plans Picked Up 6/22/2021 APPLICANT
CofO in Progress 4/18/2023 ENRIQUE MIRELES
CofO in Progress 4/18/2023 ENRIQUE MIRELES
CofO Issued 8/10/2023 DEROLD HAUFF
Permit Finaled 8/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/23/2020 RIDWAN HARDY
Construction within easement Cleared 4/23/2020 RIDWAN HARDY
Address approval Cleared 8/31/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 8/31/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/3/2020 THOMAS LANG
Sewer availability Cleared 9/3/2020 THOMAS LANG

Contact Information

Contractor Whittington Matthew; Lic. No.: 683085-B 5722 MUSCATEL AVE      SAN GABRIEL, CA 91775

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/27/2021 Not Ready for Inspection HORACE FULTZ
Footing/Foundation/Slab 2/8/2022 Corrections Issued SHAVONNE ESPINOZA
Pre-Inspection 2/14/2022 Corrections Issued FREDDIE RIVERA
Underground Mechanical 3/10/2022 Partial Approval FREDDIE RIVERA
Pre-Inspection 3/15/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/25/2022 Approved ENRIQUE MIRELES
Wood Frame 10/6/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 11/9/2022 Approved ENRIQUE MIRELES
Insulation 11/16/2022 Corrections Issued RYAN SALAZAR
Insulation 11/22/2022 Approved ENRIQUE MIRELES
Drywall Nailing 12/7/2022 Approved ENRIQUE MIRELES
Green Building Rough 12/7/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/11/2023 Approved ENRIQUE MIRELES
Final 1/11/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/11/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 1/11/2023 Approved ENRIQUE MIRELES
Final 1/19/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 1/19/2023 Approved ENRIQUE MIRELES
Final 2/22/2023 Corrections Issued ENRIQUE MIRELES
Final 3/1/2023 OK to Issue CofO ENRIQUE MIRELES