2614 N SILVER RIDGE AVE 90039
Certificate Information: 2614 N SILVER RIDGE AVE 90039
- Application / Permit
- 20014-10000-00417
- Plan Check / Job No.
- B20LA01914
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO (E) SFD.
- Permit Issued
- Issued on 8/28/2020
- Issuing Office
- Current Status
- CofO Issued on 7/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 3/19/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 3/23/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 7/10/2020 | APPLICANT |
| Plan Check Approved | 8/5/2020 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 8/6/2020 | APPLICANT |
| Issued | 8/28/2020 | APPLICANT |
| CofO in Progress | 6/24/2021 | RUBEN SALAS |
| No Progress | 7/8/2021 | RUBEN SALAS |
| CofO in Progress | 7/22/2021 | DEROLD HAUFF |
| Permit Finaled | 7/22/2021 | DEROLD HAUFF |
| Permit Finaled | 7/22/2021 | DEROLD HAUFF |
| CofO Issued | 7/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/5/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 7/9/2020 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 7/17/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2020 | WALLIE JONG |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Wavering,, Derek Evan; Lic. No.: S6239 | 1371 COLE LANE UPLAND, CA 91784 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 9/11/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/7/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 10/7/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/7/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 10/7/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/7/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/14/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 10/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 10/14/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/14/2020 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 10/14/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 10/21/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/21/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 10/21/2020 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 10/21/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 11/5/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/19/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Final | 1/27/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 1/27/2021 | Approved | SCOTT FINNILA |
| MERV13>=Final | 1/27/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 1/27/2021 | Approved | SCOTT FINNILA |
| Final | 5/11/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 5/24/2021 | Conditional Approval | KATHRYN BUTTERWORTH |
| Final | 6/1/2021 | Conditional Approval | RUBEN SALAS |